DCSIMG



​The 138 kV Kilgore Substation Project is proposed to serve new load in the Baytown/Mont Belvieu area.  The area is highly industrialized with several chemical facilities and is experiencing a significant distribution load increase with multiple new commercial and residential developments.  It is forecasted to have an approximate 25% load growth between 2021 and 2026.  The new transmission line and the Kilgore Distribution substation will supply part of this increase in distribution load.


Project updates


August 30, 2023

Application filed with the Public Utility Commission of Texas

CenterPoint Energy, Houston Electric (CEHE) filed an application with the Public Utility Commission of Texas (PUC) on August 30, 2023, to amend its Certificate of Convenience and Necessity (CCN) for the 138 kV Kilgore Substation Project. The application includes 20 alternative routes that range from approximately 2.27 to 5.66 miles. The route order is numerical and does not signify any preference on CEHE’s part as to which route is ultimately approved.

In the application, CEHE and our routing consultant, HALFF identified Route 10 (consisting of segments A2-B3-C5-D5-E5-I3-I2-K4-N31-N33) as the route that best addresses the PUC’s routing criteria. CEHE and HALFF based this on Route 10 being the third shortest route, affects 39 habitable structures within 300 feet of the centerline of the project of which 30 are industrial/commercial buildings, crossed no parks or recreational areas, has the least stream crossings, crossed no archeological sites and a high percentage of the route parallels existing ROW and property lines.

All routes, route segments and substation sites included in the application are available for selection and approval by the PUC. The deadline for intervention in PUC docket No. 55365 is September 29, 2023. The PUC will have 180 days to approve a route.

Below is the application that was filed with the PUC. You may also find the filing on the PUC’s website at Interchange - Filings (texas.gov)​

CCN Application Documents (Docket #55365)

  1. Kilgore Substation CCN Application filed with the PUC​
  2. Attachment 1 - Environmental Assessment and Alternative Route Analysis for the 138 kV Kilgore Substation
  3. Appendix A - Agency and other correspondence
  4. Appendix B - Public Meeting Information
  5. Appendix C - Table 4-1 Environmental and Land Use Data for the Proposed Alternative Routes
  6. Appendix C - Tables 4-2 through 4-6
  7. Appendix D - Kilgore Substation Fig 4-1 Constraints Map
  8. Attachment 2 - Franchise Agreement with Mont Belvieu and Baytown
  9. Attachment 3 - Cost Estimate
  10. Attachment 4 - New 138 kV Kilgore Substation Study
  11. Attachment 5 - Schematic of CenterPoint Energy's Existing Transmission System
  12. Attachment 6 - Directly affected Landowner list including habitable structures and landowner map
  13. Attachment 6 - Directly affected landowner map
  14. Attachment 7 - Written Direct Notice to Landowners
  15. Attachment 8 - Written Direct Notice to Electric Utilities located within five miles
  16. Attachment 9 - Written Direct Notice to pipeline owners paralled or crossed
  17. Attachment 10 - Written Direct Notice to County and Municipal Authorities and List of officials notified
  18. Attachment 11 - Written Direct Notice to the Office of Public Utility Counsel
  19. Attachment 12 - Written Direct Notice to the Department of Defense Military Aviation and Installation Assurance Siting Clearinghouse
  20. Attachment 13 - Newspaper Notices
  21. Attachment 14 - Transmittal Letter to Texas Parks and Wildlife Department
  22. Attachment 15 - Affidavit of Bradley J. Diehl

October 13, 2022

Public Meeting

Baytown Community Center

2407 Market Street

Baytown, TX 77520

Time:  5 p.m. – 8 p.m.

CenterPoint Energy will host a public meeting to share information as well as gather input from the public on the yet-to-be-determined route of a proposed 138 kV transmission line in northwestern Chambers County that will improve the electric reliability of the distribution system in the Mont Belvieu-Baytown Area and serve projected load growth.  Representatives from CenterPoint Energy and our routing consultant, Halff Associates will be able to answer questions and discuss the project.

The proposed construction includes a new 138 kV double-circuit transmission line between an existing CenterPoint Energy transmission line located in northwestern Chambers County to one of the three proposed Kilgore Substation sites.  The information gathered will be used to help formulate alternate routes for consideration by the Public Utility Commission of Texas.


Frequently asked questions


Who is CenterPoint Energy Houston Electric, LLC?

CenterPoint Energy Houston Electric, LLC (CenterPoint Energy or the Company) maintains the wires, towers, poles, and electric infrastructure serving more than two million end-use customers in a 5,000-square-mile electric service territory in the Houston metropolitan area. While the Company’s employees ensure the reliable delivery of electricity from power plants to homes and businesses, the Company neither generates nor sells it to customers. The Company is an indirect, wholly-owned subsidiary of CenterPoint Energy, Inc.

Headquartered in Houston, Texas, CenterPoint Energy, Inc. is a domestic energy delivery company that includes electric transmission & distribution, natural gas distribution and energy services operations. The company serves nearly seven million metered customers primarily in Indiana, Louisiana, Minnesota, Mississippi, Ohio, and Texas. With more than 9,600 employees, CenterPoint Energy, Inc. and its predecessor companies have been in business for more than 140 years.

What is the Public Utility Commission of Texas (PUC)?

The PUC is the state agency created by the Texas Legislature to regulate the rates and services of electric, telecommunication and water utilities throughout the state.

What is the Electric Reliability Council of Texas (ERCOT)?

ERCOT manages the flow of electric power to 26 million Texas customers, representing 90 percent of the state's electric load. CenterPoint Energy’s service territory is located within the footprint of ERCOT. As the independent system operator for the region, ERCOT oversees activities related to the reliable and safe transmission of electricity by scheduling power on an electric grid that connects more than 52,700 miles of transmission lines and more than 1,030 generation units. ERCOT is a membership-based nonprofit corporation, governed by a board of directors and subject to oversight by the PUC and the Texas Legislature. ERCOT's members include consumers, cooperatives, generators, power marketers, retail electric providers, investor-owned electric utilities (transmission and distribution providers including CenterPoint Energy), and municipally-owned electric utilities.

What are transmission lines?

Transmission lines are a part of the interconnected power system that moves electricity from generators to substations, where the electricity is reduced in voltage and then delivered to end-use consumers over the distribution system that connects to businesses and homes. Transmission lines are larger, operate at higher voltages, and typically convey electricity over longer distances. Distribution lines are smaller, operate at lower voltages, and convey electricity over shorter distances within cities and neighborhoods.

What is the 138 kV Kilgore Substation Project?

The 138 kV Kilgore Substation Project is a 138 kV double circuit electric transmission line proposed to be built by CenterPoint Energy between an existing CenterPoint Energy transmission line located in northwestern Chambers County and one of three proposed Kilgore Substation sites. The need for and route of the project is subject to approval by the PUC.

Where will the 138 kV Kilgore Substation be located?

The Kilgore Substation is proposed to be located near Kilgore Parkway and the Grand Parkway in northwestern Chambers County. There are three sites under consideration. The PUC will ultimately determine the route of the transmission line and the related substation location.

Why is the 138 kV Kilgore Substation Project needed?

The 138 kV Kilgore Substation is needed to meet the growing demand for electricity in the Baytown and Mont Belvieu area. The area has had substantial growth in industrial facilities, and in commercial and residential electrical load.

What is the process for the approval of the 138 kV Kilgore Substation transmission line?

CenterPoint Energy will gather input from the community through a public meeting process and other sources for the preparation of a routing study and environmental assessment between CenterPoint’s existing transmission line and the three proposed substation sites in Chambers County. After that information is gathered and the public meeting process is concluded, CenterPoint Energy will prepare and file an Application for a Certificate of Convenience & Necessity (CCN) for a Proposed Transmission Line with the PUC. The application will include multiple routing alternatives for the proposed transmission line between the existing transmission line and the proposed substation sites. The PUC will decide whether the application should be approved and, if approved, which route and substation site will be approved.

What are the considerations involved in selecting a route for the transmission line?

The PUC considers many factors in deciding whether to approve a proposed transmission line as prescribed by state law and PUC rules, including community values, recreational and park areas, historic and aesthetic values, and environmental integrity. It also considers specific routing criteria for new transmission lines, including whether the route utilizes or parallels compatible rights-of-way such as existing electrical facilities, roads, highways, railroads, telephone lines, property lines, natural features, and cultural features. CenterPoint Energy will provide information about these factors for each of the proposed alternative routes in its CCN application.

What type of structures will be used on the new transmission line?

The typical structures for the proposed alternative route segments may be double-circuit lattice steel towers, double-circuit steel poles, or double-circuit concrete poles with a vertical phase configuration in an 80-foot wide right-of-way (ROW). Depending on the terrain and other considerations, such as the length of span between structures and clearance requirements needed to cross rivers, wetland areas, Federal Aviation Administration determinations or utility and roadway crossings, CenterPoint Energy may require wider ROW widths and may vary structure types and heights.

Will CenterPoint Energy hold a Public Meeting?

Yes. Consistent with PUC rules and prior to filing a CCN application, CenterPoint Energy will hold a public meeting for the project to address concerns or questions from landowners and other interested parties. CenterPoint Energy will share information about routing alternatives and gather input from the public. Individuals attending the public meeting will have an opportunity to make comments, ask questions, and express any concerns that they might have about the routes under consideration. Representatives from CenterPoint Energy and Halff Associates will be present at the public meeting. The public meeting will be held on Thursday, Oct. 13, 2022, from 5 p.m. to 8 p.m. at the Baytown Community Center at 2407 Market Street, Baytown, TX 77520.

How will CenterPoint Energy compensate landowners if it is necessary for the transmission line to cross their property?

Once the PUC has approved a route for the project, CenterPoint Energy will make a bona fide offer to the landowner when purchasing right-of-way following the requirements of Texas law and will provide landowners with a copy of the State of Texas Landowner’s Bill of Rights. In cases where the parties do not agree on the value of the property, the land value will be determined in a condemnation proceeding where special commissioners, appointed by a judge, will determine the value of the property following a hearing where all interested parties are entitled to provide evidence of valuation.



Electric & Magnetic Fields (EMF)

Other Related Links


Contact Us

Wes Padgett

Kilgore Substation Project CCN Project Manager, CenterPoint Energy


Policy and Compliance, 

CNP-T 14th Floor 

P.O. Box 1700

Houston, TX 77251-1700


Phone: (713) 207-6490
Send email


Additional information related to the project will be added to this page as it becomes available. Please check back regularly for updates.