Project Status - Minneapolis - Nokomis Area



6/30/2020

CenterPoint Energy’s authorized contractors have finished the Nokokmis Area project. Michels Corporation finished the natural gas work and Q3 Contracting restored the areas affected by Michels Corporation’s work.

CenterPoint Energy will perform another project near the Nokomis Area project. It will happen on Woodlawn Boulevard from 50th Street E. to Minnehaha Parkway and on Minnehaha Parkway from Woodlawn Boulevard to 34th Avenue S. The anticipated duration is eight weeks for the natural gas work, with restoration to follow. The start date is TBD and will be updated on this web page.

We appreciate your patience during the construction process and wish you a safe season!



6/17/2020

This summer, crews from Michels Corporation, CenterPoint Energy’s authorized contractor, anticipate performing natural gas work on Woodlawn Boulevard from 50th Street E. to Minnehaha Parkway and on Minnehaha Parkway from Woodlawn Boulevard to 34th Avenue S. This work will include replacing natural gas mains, connecting natural gas service lines, and moving any inside residential meters to the outside of homes. The tentative start date is mid-July and the anticipated duration is eight weeks for the natural gas work, with restoration to follow.

Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to restore the other areas in the Nokomis Area project affected by Michels Corporation’s work. This week the concrete areas will be restored. In the next two weeks, the yards and boulevards will be restored.

We appreciate your patience as we continue to upgrade our natural gas lines. 



5/28/2020

  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have connected all the project’s natural gas service lines to the new mains. In the week of June 1, the crews will work at three locations to put the existing natural gas mains out of service.
  • Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to restore the areas affected by Michels Corporation’s work, working from the project’s west end to the east end.
  • For a separate job within the Nokomis Area project, the crews from Michels Corporation will replace a natural gas main on the north and south ends of the Nokomis Area project. 



5/1/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are continuing to connect natural gas service lines to the new mains in the project’s area west of 28th Avenue S.

Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, have been restoring the areas affected by Michels Corporation’s construction, working from west to east in the project area. 



4/24/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have been and will continue to connect natural gas service lines to the new mains in the following areas:

  • Currently the crews are working on 31st, 32nd and 33rd Avenues S. between 54th and 55th Streets E.
  • In the past few weeks the crews worked on 23rd and 24th Avenues S. between 54th and 56th Streets E. and on Nokomis Avenue S. between 54th and 55th Streets E.
  • Because of COVID-19 protocol in mid- to late March, the crews delayed inside meter work on 23rd and 24th Avenues S. In the week of April 27, they will return to these areas to complete the meter work.
  • Afterward the crews will work along the following areas:
    • Woodlawn Boulevard between Minnehaha Parkway and 58th Street E.
    • The area between Woodlawn Boulevard and 33rd Avenue S. and between Minnehaha Parkway and 50th Street E.
    • The area between 50th and 58th Streets E. and between 29th and 34th Avenues S.



4/21/2020

 

Installing replacement gas mains: According to the Governor of Minnesota’s order, gas main replacement is an essential work function. This allows for the modernization of related gas facilities. The gas main work requires excavations in various locations in the right-of-way (front yard) to facilitate the installation work.
 
Connecting service lines to the new mains: As social distancing practices and proper use of PPE, face masks and gloves have become normalized and as customers are willing to allow properly protected personnel into their homes to complete required work to modernize gas facilities, which is essential work, CenterPoint Energy authorized contractors will enter customer homes to complete work only with customer permission. Please see our flyer here: 


The purpose of this flyer is to advise that with customer permission, crews will now enter homes to complete necessary gas meter work. If you choose not to allow crews to enter your home, gas service will not be interrupted, and we will reschedule for a time better suited to concerns you may have. Crews will continue to replace service lines. Crews may have to dig in the ground on your property in the utility easement and next to your home to complete the task of service line replacement.



4/2/2020

Due to coronavirus concerns, CenterPoint Energy is delaying meter work that requires entering customer homes or disrupting customer gas service until further notice.


Project description: In 2019, CenterPoint Energy began its Nokomis Area project. This year CenterPoint Energy’s authorized contractors will return to complete the project. Crews from Michels Corporation will replace the remaining natural gas mains and connect the remaining natural gas service lines to the new mains. Crews from Q3 Contracting will restore the areas affected by Michels Corporation’s work.
 
Connecting service lines to the new mains: On April 6, the crews will begin connecting the project’s remaining service lines to the new mains. On the map above, work will take place in two areas: 1) between Minnehaha Parkway and 50th St. E. and between 27th and 35th Avenues S. and 2) between 52nd and 58th Streets E. and between Nokomis and 35th Avenues S.
 
Due to coronavirus concerns, CenterPoint Energy is delaying work that requires entering customer homes, such as moving gas meters outside. Gas service will not be interrupted. Crews will continue to replace service lines. A new service line will be replaced from the new main up to the resident’s home. The meter, whether it is currently inside or outside, will not be disrupted. Crews may have to dig in the ground on your property in the utility easement and next to your home to complete the task of service line replacement. At a later date, the crews will come back to add the new meter onto the service line.
 
For approx. four weeks, Michels Corporation will be performing service line work outside the homes. When the crews return to perform inside meter work and to connect the meter to the service line, the timeline will be provided on this web page.
 
Traffic impacts: When the crews are connecting the service lines to the new mains, the crews will be working on one side of the road at a time. Parking will not be available on the side where active construction is occurring. These restrictions are anticipated in areas where active construction is occurring and are necessary to keep both the public and construction personnel safe. Local access will be maintained. 



3/27/2020

In the last quarter of the 2019 construction season, CenterPoint Energy’s authorized contractor, Q3 Contracting, temporarily restored the areas affected by CenterPoint Energy’s construction due to freezing weather that was unconducive for permanent restoration. Between late March and early summer 2020, crews from Q3 Contracting are returning to these projects to permanently restore the areas affected by CenterPoint Energy’s construction that ended in 2019.

For CenterPoint Energy’s Nokomis Area job, Q3 Contracting will start on the project’s west end working east. Due to COVID-19 protocol, Q3 Contracting will continue to restore the hard surfaces affected by CenterPoint Energy’s work. The soft surfaces affected by CenterPoint Energy’s work will be restored if they would otherwise become a safety hazard. Once the stay home order is lifted, the crews will resume completing all soft surface restoration.

Thank you from all of us at CenterPoint Energy for your patience. We look forward to another successful construction season this year!



12/16/2019

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have finished the project’s natural gas work for 2019.

Natural gas main installations
In 2020, the crews will replace natural gas mains on Minnehaha Parkway between 27th and 34th Avenues S. and on Woodlawn Boulevard between Minnehaha Parkway and 50th Street E.

Natural gas service line connections
In 2020 the crews will resume the connections primarily between 52nd and 58th Streets E. and between 29th and 34th Avenues S. They will also be working throughout the project in any areas that didn’t have connections this year.

Restoration
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to follow Michels Corporation’s route, temporarily restoring the areas affected by Michels Corporation’s construction. They anticipate finishing temporary restoration this month. For examples of temporary and permanent restoration, please see our restoration web page



12/13/2019

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are finishing the natural gas work for 2019. Due to weather, the crews’ progress and agreements between CenterPoint Energy and the City of Minneapolis, the crews will resume any remaining natural gas work in 2020.

Natural gas main installations
By December 20, the crews will have finished the project’s natural gas main installations except for Minnehaha Parkway between 27th and 34th Avenues S. and on Woodlawn Boulevard between Minnehaha Parkway and 50th Street E.

Natural gas service line connections
This week, the crews have finished the 2019 connections. Next year they’ll resume the connections primarily between 52nd and 58th Streets E. and between 29th and 34th Avenues S. They will also be working throughout the project in any areas that didn’t have connections this year. 

Restoration
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to follow Michels Corporation’s route, temporarily restoring the areas affected by Michels Corporation’s construction. For examples of temporary and permanent restoration, please see our restoration web page



12/3/2019

Natural gas main installations
Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are continuing to replace natural gas mains. They are currently working on the streets between 57th and 58th Streets E., including Bossen Terrace, Sander Drive, 33rd Avenue S. and 58th Street E. Afterward the last of the project’s streets to have mains replaced are Minnehaha Parkway between 27th and 34th Avenues S., and Woodlawn Boulevard between Minnehaha Parkway and 50th Street E.

Natural gas service line connections
The crews are continuing to connect natural gas service lines to the new mains between 50th and 55th Streets E. and between 29th and 34th Avenues S.

Restoration
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to follow Michels Corporation’s route, temporarily restoring the areas affected by Michels Corporation’s construction. For examples of temporary and permanent restoration, please see our restoration web page



11/22/2019

Natural gas main installations
  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are continuing to replace natural gas mains primarily along the project’s streets south of 54th Street E.
  • Additional locations are Shoreview Avenue and 23rd and 24th Avenues S. between 54th and 55th Streets E. Here the crews will replace natural gas main and connect natural gas service lines to the new main.
  • The crews will replace natural gas main along Minnehaha Parkway between 27th and 34th Avenues S. and Woodlawn Boulevard between Minnehaha Parkway and 50th Street E.
Natural gas service line connections
  • The service line crews are following the main crews’ routes. Some of the areas are between 50th and 54th Streets E. and between 28th and 32nd Avenues S.
Restoration
  • Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to follow Michels Corporation’s route, temporarily restoring the areas affected by Michels Corporation’s construction. For examples of temporary and permanent restoration, please see our restoration web page



11/15/2019

Natural gas main installations
Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are continuing to replace natural gas mains along the project’s streets south of 54th Street E.

Service line connections
The crews are continuing to connect natural gas service lines between 50th and 54th Streets E. and between 28th and 31st Avenues S., as well as Woodlawn Boulevard and 26th Avenue S.

Restoration
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to follow Michels Corporation’s route, temporarily restoring the areas affected by Michels Corporation’s construction. For examples of temporary and permanent restoration, please see our restoration web page.



11/8/2019

Natural gas main installations
Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced natural gas mains along the project’s streets between Minnehaha Parkway and 54th Street E., as well as Woodlawn Boulevard and Shoreview Avenue. The crews will be replacing mains along the project’s streets south of 54th Street E.

Service line connections
The service line crews are following the main crews’ routes. Some of the areas include 29th and 30th Avenues S. between Minnehaha Parkway and 52nd Street E., as well as Woodlawn Boulevard and 26th Avenue S.

Restoration
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to follow Michels Corporation’s route, temporarily restoring the areas affected by Michels Corporation’s construction. For examples of temporary and permanent restoration, please see our restoration web page. 



10/31/2019

Natural gas main installations
  • Within the first or second week of December, crews from Michels Corporation, CenterPoint Energy’s authorized contractor, anticipate replacing the final of the project’s natural gas mains.
  • Currently the crews are replacing mains between 54th Street E. and Minnehaha Parkway and between 29th and 33rd Avenues S., in addition to Woodlawn Boulevard at 26th Avenue S. When they are done in this area, they will transition to the project’s southeastern corner south of E. 54th Street between Nokomis Avenue and 34th Avenue S.
Service line connections
  • The crews are connecting residents’ natural gas service lines to the new mains, closely following the main crews’ routes. The crews are currently in the project’s northwest corner, primarily along 30th Avenue S. between 52nd Street E. and Minnehaha Parkway.
Restoration
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, have restored the following areas:

  • The concrete work is done along Woodlawn Boulevard from 52nd to 56th Streets E. and along most of Shoreview Avenue.
  • The crews have restored the yards and boulevards with black dirt and seed along 52nd Street E. between 27th Avenue S. and Woodlawn Boulevard.
Temporary restoration
  • Due to weather, the crews are beginning to restore the areas affected by Michels Corporation’s construction with temporary restoration. For examples of temporary and permanent restoration, please see our restoration web page.
  • Many of the areas that received permanent concrete restoration should expect to receive permanent soft surface restoration. If the crews are unable to perform permanent soft surface restoration in 2019, they will apply hydroseed in 2019 and return in 2020 to replace with black dirt and seed.
  • Any concrete areas that have yet to receive permanent restoration will receive temporary asphalt restoration in 2019 and permanent restoration in 2020. In these areas, the affected lawns and boulevards will receive hydroseed in 2019 and black dirt and seed in 2020.  



10/23/2019

Natural gas main installations
Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced natural gas mains along both sides of the project’s streets from 29th to 33rd Avenues S. between 50th Street E. and Minnehaha Parkway. The crews will be replacing main on Minnehaha Parkway from Woodlawn Boulevard to 34th Avenue S. and in the project’s streets from 29th to 34th Avenues S. between 52nd and 54th Streets E.

Service line connections
  • The crews are continuing to connect natural gas service lines to the new mains in the following areas for the next several weeks:
    • 30th Avenue S. between 50th and 52nd Streets E.
    • Between 50th and 54th Streets E. and between 31st and 34th Avenues S.
    • Between 49th and 53rd Streets E. and between 29th and 33rd Avenues S.
Due to the crews’ progress, weather and agreements between CenterPoint Energy and the City of Minneapolis, the project’s natural gas main work is expected to last into December 2019. We appreciate your patience as we replace our infrastructure. 



10/16/2019

Natural gas main installations
  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have finished replacing most of the natural gas mains along the streets between 28th Avenue S. and Woodlawn Boulevard and between 50th and 54th or 56th Streets E.
  • Currently they are working between 29th and 31st Avenues S. and between 50th and 54th Streets E. for several weeks.
Service line connections
  • The crews are working in the following areas for the next several weeks:
    • 30th Avenue S. between 50th and 52nd Streets E.
    • Between 50th and 54th Streets E. and between 31st and 34th Avenues S.
    • Between 49th and 53rd Streets E. and between 29th and 33rd Avenues S. 



10/7/2019

Natural gas main replacements
  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced natural gas mains along the north and south sides of Keewaydin Place, E. 51st Street and Weenonah Place between 31st and 34th Avenues S. They also connected the new mains to the existing ones on 26th Avenue S. and E. 52nd Street.
  • This week the crews plan to replace the rest of the natural gas main on E. 52nd Street between Woodlawn Boulevard and 33rd Avenue S. When one crew is done in this area, they will transition to the streets from 29th to 31st Avenues S. between 50th and 52nd Streets E.
  • The crews are currently replacing natural gas mains on 29th and 30th Avenues S. Over this weekend, the crews will work on 30th Avenue S. near Keewaydin Elementary School.
Natural gas service line connections
  • The crews are connecting the final of the natural gas service lines to the new mains on Woodlawn Boulevard and Shoreview Avenue. When these connections are done, the crews will put the existing natural gas mains out of service in these areas.
  • The crews are currently connecting natural gas service lines to the new mains on 26th and 27th Avenues S. and on E. 54th Street, moving north on 27th Avenue S. 



9/24/2019

Natural gas main replacements
Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced natural gas mains along the following streets:

  • The north side of Keewaydin Place between 31st and 34th Avenues S.
  • E. 52nd Street from Woodlawn Boulevard to 29th Avenue S.

The crews will continue to replace natural gas mains along the following streets:

  • E. 54th Street from Woodlawn Boulevard to 27th Avenue S.
  • 26th Avenue S. at Woodlawn Boulevard
  • The south side of Keewaydin Place between 31st and 34th Avenues S. (After this area is done with main replacements, the crews will move onto both sides of E. 51st Street between 31st and 34th Avenues S. and then Weenonah Place between 31st and 34th Avenues S.)
  • Both sides of 27th Avenue S. between 50th and 52nd Streets E. (This area will be done with main replacements next week.)

Natural gas service line connections
The crews are continuing to connect natural gas service lines to the new mains on Woodlawn Boulevard and Shoreview Avenue.



9/13/2019

Currently a crew from Michels Corporation, CenterPoint Energy’s authorized contractor, are continuing to replace natural gas mains along the following streets:

  • E. 52nd Street from Woodlawn Boulevard to 33rd Avenue S.
  • East and west sides of 26th Avenue S. between 52nd and 54th Streets E.

When the crews are done replacing natural gas main on E. 52nd Street, they will transition to the northbound and southbound streets from 29th and 31st Avenues S. between Keewaydin Place and Weenonah Place. They will also replace natural gas main on 26th Avenue S. between E. 52nd Street and Woodlawn Boulevard and on Woodlawn Boulevard between Shoreview Avenue and 27th Avenue S. (also Woodlawn Boulevard).

For several weeks the crews are continuing to connect natural gas service lines on Woodlawn Boulevard and Shoreview Avenue between 52nd and 56th Streets E. 

This weekend the crews will accommodate the St. Helena Daze Parade by removing equipment from the parade’s route on E. 52nd Street.



9/6/2019

  • Currently a crew from Michels Corporation, CenterPoint Energy’s authorized contractor, are replacing natural gas mains on both sides of 26th Avenue S. between 52nd and 54th Streets E. They will be in this area for approximately three weeks.
  • Within the week of September 9, an additional Michels Corporation crew will begin replacing natural gas main on E. 52nd Street from Woodlawn Boulevard to 33rd Avenue S.
  • For several weeks the crews are connecting natural gas service lines on Woodlawn Boulevard and Shoreview Avenue between 52nd and 56th Streets E. 



8/28/2019

  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are continuing to work on the west side of 27th Avenue S. between 50th and 54th Streets E. and on the alley between 26th and 27th Avenues S. from 51st to 52nd Streets E.
  • When they are finished with this area, they will install natural gas main on E. 52nd Street, working east toward 33rd Avenue S.
  • In the week of September 2 after Labor Day, the crews will begin connecting natural gas service lines to the new mains, following the main installation crew’s route. 



8/23/2019

  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have been connecting the new main to existing intersecting mains along Shoreview Avenue at E. 52nd Street and E. 56th Street and along E. 52nd Street at 27th Avenue S.
  • By approximately the end of the week of August 26, the crews will have replaced natural gas mains and connected them to existing intersecting mains along the following streets: Woodlawn Boulevard from E. 50th Street to E. 54th Street; 26th Avenue S. from E. 52nd Street to E. 54th Street; and E. 52nd Street from 26th Avenue S. to just east of 27th Avenue S.
  • When they are finished with these areas, they will begin replacing natural gas mains in the area that spans the following streets: between E. 50th Street and E. 52nd Street and between 29th to 34th Avenues S. 



8/16/2019

  • Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced natural gas mains along the following streets: Woodlawn Boulevard from E. 52nd Street to E. 56th Street; Shoreview Avenue between E. 52nd Street and E. 56th Street; and E. 53rd Street and E. 54th Street between Woodlawn Boulevard and Shoreview Avenue.
  • Next week the crews will begin replacing natural gas main on E. 52nd Street between Woodlawn Boulevard and 28th Avenue S.  
  • During active construction, parking will be available on the opposite side of the street from where crews are working. The crews will move the “no parking” signs as they progress. 



8/2/2019

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, will begin the Nokomis Area job this Monday, August 5. For approximately three weeks, they will replace natural gas mains on the following streets:

  • Woodlawn Boulevard from E. 52nd Street going south to E. 56th Street
  • Shoreview Avenue between E. 52nd Street and E. 56th Street
  • E. 53rd Street and E. 54th Street between Woodlawn Boulevard and Shoreview Avenue
During active construction, parking will be available on the opposite side of the street from where crews are working. The crews will move the “no parking” signs as they progress. 



7/15/2019

Where, when, and why is CenterPoint Energy performing construction?
  • From the week of August 5 to spring or summmer of 2020, CenterPoint Energy’s authorized contractor, Michels Corporation, will be replacing natural gas mains and connecting natural gas service lines to the installed mains in Minneapolis along selected streets between E. Minnehaha Parkway and E. 54th Street and between Woodlawn Boulevard and 34th Avenue S.
  • Residents will have access to their properties.
  • Construction will occur in segments along the construction route, rather than all at once. Lane restrictions are anticipated in areas where active construction is occurring and are necessary to keep both the public and construction personnel safe.
  • CenterPoint Energy’s authorized contractor, Q3 Contracting, will restore the areas affected by Michels Corporation’s construction—typically the utility easement, the street, and the customer’s yard.

How may the natural gas service line installations affect customers?

  • As part of this main project, the crews will be replacing several natural gas service lines that connect from the main to the customer’s property. Customers will experience a short disruption of gas service as the crews are installing the gas service line.
  • Crews may have to dig in the ground on your property in the utility easement to complete the task of service and main distribution line replacement. If a customer’s property is disturbed, CNP will restore the hard and soft surfaces affected by construction at no cost to you.
  • In addition to the natural gas service line installation, some customers may also have their inside gas meters moved to the outside of their homes as part of CenterPoint Energy’s long-term improvement project called “Moving Gas Meters Outside.” Please click here to find out more about our project and click here to see a one-page fact sheet with photographs of a meter move. 

What is CenterPoint Energy’s mission, and how can I contact CenterPoint Energy?

At CenterPoint Energy, we are committed to providing timely and relevant information to our customers and the general public to minimize inconvenience or disruption due to our construction activities. CNP has provided safe, clean and efficient natural gas service to Minnesota communities for more than 145 years. We are proud of this record and strive to improve it by educating the public about the benefits of natural gas at CenterPointEnergy.com/BeSafe.

Updates will be posted on this Project Status page. For any questions, you can contact one of the following resources:
Restoration Questions

Please reference the project name or number 88104238 when calling. We appreciate your business and look forward to continuing to serve you. Thank you very much.