Project Status - Edina - Abbot Avenue S. and 59th Street W. Neighborhood


7/31/2019

CenterPoint Energy’s authorized contractor, Q3 Contracting, is continuing to restore the soft surface areas affected by Michels Corporation outside the limits of the city’s project. Contractors for the City of Edina are working on the city’s “Chowen Park A & B Roadway Reconstruction” project. For more information on it, please visit its website. CenterPoint Energy appreciates your patience as we progress in construction.


7/2/2019

Crews from CenterPoint Energy’s authorized contractor, Michels Corporation, have connected all the project’s natural gas service lines to the installed mains. Today on Tuesday, July 2, the crews are putting the existing natural gas main on Beard Avenue S. out of service. This will complete Michels Corporation’s natural gas work for the project.  

Following the Michels Corporation crews is construction by contractors for the City of Edina for the city’s “Chowen Park A & B Roadway Reconstruction.” CenterPoint Energy’s authorized contractor, Q3 Contracting, will restore the soft surface areas affected by Michels Corporation outside the limits of the city’s project. For more information on the city’s project, please visit its website.

CenterPoint Energy appreciates your patience as we progress in construction. 



6/12/2019
Crews from CenterPoint Energy’s authorized contractor, Michels Corporation, have connected natural gas service lines to the installed mains along Ewing, Drew, Zenith, York and Chowen Avenues S. The crews are currently connecting service lines on Beard and Abbot Avenues S. The crews anticipate finishing the service line connections by approximately the end of June. 

Further construction is being done by contractors for the City of Edina for the city’s “Chowen Park A & B Roadway Reconstruction.” CenterPoint Energy’s authorized contractor, Q3 Contracting, will restore the soft surface areas affected by Michels Corporation outside the limits of the city’s project. For more information on the city’s project, please visit its website. 



5/17/2019
Since last week, CenterPoint Energy’s authorized contractor, Michels Corporation, have been connecting natural gas service lines to the installed mains along Ewing and Drew Avenues S. between W. 58th Street and W. 60th Street. The crews will continue working in these areas into the first half of next week. Within the second half of the week of May 20, the crews will begin the service line connections on York Avenue S.

Further construction will be done by contractors for the City of Edina for the city’s “Chowen Park A & B Roadway Reconstruction.” Bituminous Roadways, Inc. is currently working behind the Michels Corporation crews. CenterPoint Energy’s authorized contractor, Q3 Contracting, will restore the soft surface areas affected by Michels Corporation outside the city limits. For more information on the city’s project, please visit its website. 



5/6/2019
CenterPoint Energy’s authorized contractor, Michels Corporation, will be installing the final of the natural gas mains this week for CenterPoint Energy’s “Abbot Avenue S. and 59th Street W. Neighborhood” project. Also this week, the crews will begin connecting natural gas service lines to the installed mains. The crews will be performing these connections for the next few weeks. 



4/11/2019

Where, when, and why is CenterPoint Energy performing construction?

From the week of April 15 to late July 2019, CenterPoint Energy’s authorized contractor, Michels Corporation, will be replacing natural gas mains and connecting natural gas service lines to the installed mains in Edina in the Abbot Avenue S. and 59th Street W. neighborhood.
 
Further construction will be done by contractors for the City of Edina for the city’s “Chowen Park A & B Roadway Reconstruction.” Nearby construction by the city will involve the “West 58th Street Reconstruction” project. For more information on each project, please visit its respective website.

What are the estimated traffic impacts?

  • Residents and local businesses will have access to their properties.
  • Construction will occur in segments along the construction route, rather than all at once. Lane restrictions are anticipated in areas where active construction is occurring and are necessary to keep both the public and construction personnel safe.
  • CenterPoint Energy’s authorized contractor, Q3 Contracting, will restore the areas affected by Michels Corporation’s construction—typically the boulevard, lawn, sidewalk and road.

How may the natural gas service line installations affect customers?

  • As part of this main project, the crews will be replacing several natural gas service lines that connect from the main to the customer’s property. Customers will experience a short disruption of gas service as the crews are installing the gas service line.
  • Crews may have to dig in the ground on your property in the utility easement to complete the task of service and main distribution line replacement. If a customer’s property is disturbed, CNP will restore the hard and soft surfaces affected by construction at no cost to you.
  • In addition to the natural gas service line installation, some customers may also have their inside gas meters moved to the outside of their homes as part of CenterPoint Energy’s long-term improvement project called “Moving Gas Meters Outside.” Please click here to find out more about our project and click here to see a one-page fact sheet with photographs of a meter move. 

What is CenterPoint Energy’s mission, and how can I contact CenterPoint Energy?

At CenterPoint Energy, we are committed to providing timely and relevant information to our customers and the general public to minimize inconvenience or disruption due to our construction activities. CNP has provided safe, clean and efficient natural gas service to Minnesota communities for more than 145 years. We are proud of this record and strive to improve it by educating the public about the benefits of natural gas at CenterPointEnergy.com/BeSafe.

Updates will be posted on this Project Status page. For any questions, you can contact one of the following resources:

Communications Specialist
  • Hannah Gullickson – 612-321-5546
Information Hotline
Restoration Questions

Please reference the project name or number 88014626 when calling. We appreciate your business and look forward to continuing to serve you. Thank you very much.