Fountain Ln N & Everest Ln N - 11/14/25

NPL crew will be finish with the project today (gas main, services and main abandonments).


For restoration NPL crew has done some of the soft surface within the project, the crew will be back next week to do concrete-blacktop and finish up with the black dirt and seed w/blanket. Crew will be moving equipment off site Monday (11-17-25)


Fountain Ln N & Everest Ln N - 10/16/25

Main was installed and gas up on Fountain Ln and Garland Ln N. The crew will be starting this week installing services on Fountain Ln


Crew started services on 28th Ave N and Everest Ln N last Thursday 10-16-25.


36 Avenue North: 4/28/2025

Construction is complete on Trenton Lane North and Saratoga Lane North. The main crew is moving east along 36th Avenue North towards Kilmer Lane North and expects to be complete by the end of next week.


A service crew will be in the area following the installation of new main. They will work to replace and connect service lines to the new main and move inside meters outside.


Lane shifts are in place along 36th Avenue North. Expect to see both CenterPoint contractors and the City’s contractors performing work in the area at this time.

What will CenterPoint Energy do?

Construction in areas of Plymouth will begin at the end of March and last a few months. Updates for both projects can be found on this page.


Before construction begins, an authorized contractor will be in the area to locate sewer lines in relation to natural gas lines. This is an important safety measure CenterPoint is required to take. It is possible a technician performing this work will need to access your home to locate sewer lines. Ask to see CenterPoint Energy identification before letting anyone in your home.