Natural Gas Infrastructure Upgrades in Fridley
We are committed to keeping our customers informed about important updates we are making to our infrastructure – designed to enhance safety, improve reliability, and continue to provide you with the energy you need for life's moments. The following outlines the work we plan to complete this summer in Fridley.
Project resources
Overview
E River Rd
Beginning as early Mid-September, CenterPoint Energy will upgrade natural gas infrastructure along E River Rd. This work is expected to last up to 2 months.
Osborne Rd
Beginning in early May and ending in late July, CenterPoint Energy will make upgrades to a large diameter transmission pipe that lies within CenterPoint's easement. There will be no service work or service interruptions associated with this project.

Contractor summary
CenterPoint works with multiple contractors to complete construction projects in a safe and timely manner. You will see these contractors working in your area and may be contacted by them at various stages in the construction process.
For more information about authorized contractors click here.
Marking utilities
CenterPoint Energy will locate public underground utilities. This is an important safety preparation, done before construction begins. The utilities will be marked with spray paint and flags. If you have installed any private lines such as sprinklers or dog fences, we ask that you mark them with a material that is convenient for you. Examples include spray paint, flags, and wooden sticks used to stir paint. Marking sprinkler heads is sufficient. If any utility flags are left in residents' yards after restoration is complete, they may be removed and thrown away.
Natural gas main work
Plastic mains reaching the end of their useful life are replaced with modern plastic piping that increases the safety and reliability of CenterPoint's gas distribution.
Plastic main is replaced by boring underneath the side of each road. Please keep in mind that some intersections may not be permanently restored until after the service work is complete. Until then, customers may see temporary backfill such as dirt or gravel
Visit the Construction Definitions page for more information.
Restoration
The final step in an infrastructure project is to restore the areas that were impacted by construction. Restoration is typically on site a few weeks after the completion of all other construction. Until then, temporary restoration is done by the utility crews to maintain an area's livability.
For more details visit the Restoration Practices page.
Transportation impacts
Trail closures will occur, and will be communicated as they are in place. The utility crews will work with residents to maintain access to their homes.
Additional Resources
If you have questions, reach out to CenterPoint Energy's Communication Specialist at 612-542-6198 or MNConstruction@centerpointenergy.com.
Thank you for your patience and understanding as we replace our infrastructure! We value the privilege of having you as a customer.