Lakeville - Kenrick Avenue


Scheduled Start Date: August 15, 2022

CNP Map of Lakeville Kenrick Ave.jpg

Project Resources

  • If you contact CenterPoint Energy for any questions, please reference the project’s name or the number 101764599.

What will CenterPoint Energy do?

From Monday, August 15 into late September 2022, CenterPoint Energy’s authorized contractors will work in Lakeville along Kenrick Avenue S. from Kenrick Loop to 175th Street W. While Michels Corporation will replace a small-diameter natural gas plastic main, connect service lines to this main, and move inside meters outside, Q3 Contracting will restore the areas affected by Michels Corporation’s work.

The crew is beginning their work at 175th Street W., working north approximately two blocks at a time.

During this time, the crews will shift lanes while maintaining two-way traffic on Kenrick Avenue. Entrances to and from business parking lots will remain open. Flaggers will be on site to help direct traffic.

CenterPoint Energy is replacing other natural gas lines on Ipava Avenue and a few select streets, including Kenrick Avenue. From Tuesday, September 6 until at least Friday, September 16, CenterPoint Energy’s authorized contractors will close northbound Kenrick Avenue from Kenrick Loop to 164th Street W. While Michels Corporation will replace a large-diameter natural gas steel main, Q3 Contracting will restore the areas affected by Michels Corporation’s work.

Constituents will still be able to access the 164th Street W. entrance to the businesses in the area. If anyone is heading north on Kenrick Avenue, they will see detour signs at 165th Street W. They’ll be detoured east on 165th Street W., north on Ipava Avenue, and west on 162nd Street W. 

Kenrick Avenue from Maple Island Road to Dunkin' Donuts

Beginning on Monday, September 19 and lasting for approximately six weeks, the following two traffic changes will occur on Kenrick Avenue:

  • Southbound traffic will be closed on Kenrick Avenue from Maple Island Road to Dunkin’ Donuts. During this time, northbound traffic will remain open, while southbound traffic will be detoured from Crystal Lake Road to Interstate 35 and to County Road 46.

  • Two-way traffic will be maintained on Kenrick Avenue from County Road 46 to Kenrick Loop. By then, the closure of northbound Kenrick Avenue in this area will have been opened.

CNP Map of Lakeville Kenrick Ave Sept and detour.png