7/2/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced the natural gas main on Bass Lake Road (County Road 10) between Major Avenue N. and Northport Drive. In the week of July 6, the crews will begin connecting the natural gas service lines to the new main. During the service line connections, the crews will continue to maintain two-way traffic on County Road 10 with a lane shift.


Also in the week of July 6, the crews will begin to replace the natural gas main on County Road 10 between Vera Cruz and Perry Avenues N. Two-way traffic will be maintained on County Road 10 with a lane shift.

6/24/2020

By the end of the week of June 29, crews from Michels Corporation, CenterPoint Energy’s authorized contractor, will have replaced the natural gas main along County Road 10 between Major and Northport Avenues N., and along Major Avenue N. between County Road 10 and 58th Place N. They will also have connected these new mains to the existing intersecting ones.


In the week of July 6, the crews will begin replacing the natural gas main on County Road 10 at Regent Avenue N., working west to Vera Cruz Avenue N.

6/4/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, began replacing the natural gas main on Monday, June 1 at Northport Drive, working west on the north shoulder of Bass Lake Road. The crews anticipate that the project’s natural gas main replacement will take approximately four or five weeks.