8/20/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, finished the project’s natural gas work. Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, restored the areas affected by Michels Corporation’s work. We thank you for your patience and wish you a safe and well season.

7/17/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have been connecting natural gas service lines to the new main on Bass Lake Road. In the week of July 20, they anticipate finishing the service line connections on that street and moving to Major Avenue N.


Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are following Michels Corporation’s route, restoring the areas affected by Michels Corporation’s work.

7/15/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, are finishing the project’s natural gas main replacement. Today on July 15, they expect to finish putting the new main in service.


The crews are continuing to connect the natural gas service lines to the new main west of Northport Drive. While they are working, they will maintain two-way traffic with a lane shift.

7/2/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, have replaced the natural gas main on Bass Lake Road (County Road 10) between Major Avenue N. and Northport Drive. In the week of July 6, the crews will begin connecting the natural gas service lines to the new main. During the service line connections, the crews will continue to maintain two-way traffic on County Road 10 with a lane shift.


Also in the week of July 6, the crews will begin to replace the natural gas main on County Road 10 between Vera Cruz and Perry Avenues N. Two-way traffic will be maintained on County Road 10 with a lane shift.

6/24/2020

By the end of the week of June 29, crews from Michels Corporation, CenterPoint Energy’s authorized contractor, will have replaced the natural gas main along County Road 10 between Major and Northport Avenues N., and along Major Avenue N. between County Road 10 and 58th Place N. They will also have connected these new mains to the existing intersecting ones.


In the week of July 6, the crews will begin replacing the natural gas main on County Road 10 at Regent Avenue N., working west to Vera Cruz Avenue N.

6/4/2020

Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, began replacing the natural gas main on Monday, June 1 at Northport Drive, working west on the north shoulder of Bass Lake Road. The crews anticipate that the project’s natural gas main replacement will take approximately four or five weeks.