​​​​​Natural Gas Service Line Installation

Guidelines

At CenterPoint Energy, we're committed to meeting your service deadlines, but we need your help. Before a natural gas service line can be installed, the following guidelines must be met at your home site. ​For future reference, please print this page and ​​keep it with your other construc​tion standards.

  • All necessary permits must be obtained from the proper authorities prior to installation of a service line.
  • The house must be piped bef​​ore requesting a service line. The service line will be installed as per the below timelines from the date the service line was requested.
  • There must be an obstruction-free, e​​ight-foot wide service pathway from the gas main line to the meter loop location. All trash bins, construction materials, etc. must be cleared from this area.
  • The address (number & street) must be posted and visible from the street.

Homebuilders may request service online using our Builder Portal. Register online today

Call 713-223-4567 or 1-800-669-8344 48 hours before any excavation work to have underground facilities located.

Call 713-659-2111 to report broken gas lines.

AreaCustomer may be contacted if further information is needed to proceed​:
Service Lines can be expected to be installed within Approximately:​ ​
Mississippi5-7 days3-4 weeks​
Houston7 days6-10 Weeks
Texas Coast7 days6-10 Weeks
Texas Rural7 days6-10 Weeks
​S.Louisiana5-7 days4-5 Weeks
N.Louisiana5-7 days15​-20 days