​​​​Project S​tatus - Wayzata - Ferndale Road

12/15/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished the remaining 900 feet of pipeline installation near Peavey Bridge.

We understand that Ferndale Road construction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete all possible restoration in the 2015 construction season. For any inquiries or concerns, please visit our website for the proper contact information.

Even though CenterPoint Energy's 2015 construction season will be coming to a close at the end of the month, please continue to visit our website during the off season as 2016 projects will be added weekly! Thank you. 


12/4/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will return onsite Monday, December 7 to complete final pipeline installation.

Crews will be working approximately 300 feet east and 600 feet west of the Peavey Bridge.

Crews anticipate completing installation of the remaining pipeline by Friday, December 11.

Due to the cold weather, crews from Q3, an authorized CenterPoint Energy contractor, will hydromulch all soft surface areas for erosion control over the winter and blacktop any needed restoration on the street. In the spring, crews will return onsite to complete final restoration. For inquiries or concerns, please call our hotline number at 612-321-5042 or visit our restoration website.

For more information, please visit our website. Thank you. ​


8/28/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe and service line replacements within the scope of this project.

Crews will return onsite to complete final construction after the Ferndale Road W. bridge reconstruction is complete.

An additional email will be sent once final dates are known.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​ ​


7/27/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of this project.

Crews will begin service line replacements along Ferndale Road W., Bovey Road and Ferndale Road S. this week.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please anticipate lane shifts and closures in the areas of construction.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​
​​

 

7/14/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contra​​ctor, have started installing natural gas distribution pipe along the north side of Ferndale Road W., working eastwards to where the road turns, to Ferndale Road S.

Tomorrow, Wednesday, July 15, crews will install natural gas distribution pipe along the east side of Bovey Road.

Crews are installing approximately 500 feet of pipe per day and anticipate installing all natural gas pipe by the end of next week.

Service line replacements will follow.

Please anticipate lane shifts and closures in the areas of construction.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​​​