Project Status - Minnetonka - County Road 101​

12/1/2014 Update​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe at the intersection of Bushaway Road, Eastman Lane and McGinty Road W. Construction will be completed next week in this area.

Service line replacements will begin shortly after. Please note that representatives from CenterPoint Energy continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

11/17/2014 Update​​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe along the east shoulder of County Road 101, between Blaine Avenue and Maple Hill Road in Minnetonka.

This week, construction will begin at the intersection of Bushaway Road, Eastman Lane and McGinty Road W. in Wayzata.

Construction is expected to be completed in three weeks, weather permitting.
Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

10/15/2014 Update​​​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, have temporarily finished construction on Eastman Lane.

In several weeks, crews will be returning to this location to finish construction under Hennepin County’s new McGinty Road W., Eastman Lane and County Road 101 intersection.

Tomorrow, County Road 101, north of Grays Bay Bridge, will be closed for the day as construction continues. Construction will continue in this area until approximately Monday, October 20th.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

10/8/2014 Update​​​

Starting today, October 9th, County Road 101 will be closed to traffic due to Hennepin County’s reconstruction project. Please follow the posted detour signs in the areas of construction. 

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue construction between County Road 101 and East Circle Drive and eastwards along County Road 16.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

9/25/2014 Update​​

Beginning today, Thursday, September 25th, County Road 16, both the east and west side of County Road 101, will be closed for approximately one month. Please follow the posted detour signs in the areas of construction.

On Monday, September 29th, crews will begin construction between County Road 101 and East Circle Drive. Crews will be starting at the southern end of Echo Drive, working across the railroad track and then heading eastwards along County Road 16.

Please re-visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

9/22/014 Update​​

Michels Corporation, an authorized CenterPoint Energy contractor, will begin replacing natural gas distribution pipe on the west side of County Road 101 today, Monday, September 22nd. CenterPoint Energy signs are in place in the areas of construction.

Crews will also be working on McGinty Road W. and working southwards toward Locust Hill Drive. On Monday, September 29th, the entrance to County Road 101 from Locust Hill Drive will be closed for two days.

Please re-visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.