​​​​​​​​​​​​​​​​​​​​Waseca - 8th Street NE

​​​Scheduled Start Date: Week of July 11, 2016

​​​​Project Description​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 7,032 feet of various diameter plastic and steel pipe with 5,700 feet of 2-inch and 4-inch plastic pipe along 5th Avenue NE, 7th Avenue NE and along 8th Street NE, from 8th Avenue NE to Elm Avenue E.

The work will also include the replacement of approximately ​105 natural gas service lines. Construction is expected to ​begin in spring or summer of 2016 and will require approximately two and a half months to complete the work. ​​​​