Project Status - St. Peter - College Avenue Neighborhood

12/13/2018
Crews from Michels Corporation, CenterPoint Energy’s authorized contractor, will be finishing their 2018 natural gas main installations by the end of the week of December 10 or 17. By then they will have installed natural gas mains between 4th Street N. and 7th Street N. and between College Avenue and Grace Street W. The crews will return in 2019 to finish the southeastern installations and service line connections.
 
Crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are continuing to temporarily restore the areas affected by Michels Corporation’s 2018 construction. The hard surfaces currently have temporary materials and will have permanent materials in 2019. The soft surfaces currently have straw mats and will have hydroseed and hydromulch in the spring.



12/4/2018
Crews from CenterPoint Energy’s authorized contractor, Michels Corporation, have installed natural gas mains on all the project streets west of Washington Street N. The crews are currently installing natural gas main along 4th Street N. and 5th Street N. between College Avenue and Grace Street W.
 
Crews from Q3 Contracting, an authorized CenterPoint Energy contractor, are following behind the crews to temporarily restore the areas affected by Michels Corporation’s construction. Permanent restoration will happen in 2019. For examples of restoration, please visit our Restoration Practices and Updates page.
 
Michels Corporation will resume the natural gas main installation and service line connections in Spring 2019. More details will be added to our website closer to the project’s 2019 start date. 



11/21/2018
Crews from CenterPoint Energy’s authorized contractor, Michels Corporation, have installed natural gas mains on all the project streets north of County Road 5. By the end of the week of November 26, the crews will have installed natural gas mains on all the project streets north and west of Washington Street.
 
The crews have also connected natural gas service lines to the natural gas main along Front Street between Walnut Street and Pine Street. 


11/1/2018

Where, when, and why is CenterPoint Energy performing construction?

CenterPoint Energy’s authorized contractor, Michels Corporation, will be replacing the natural gas system in the St. Peter neighborhood along selected streets between Madison Street W. and Stones Way, and between 8th Street N. and Front Street N. Crews from Q3 Contracting, an authorized CenterPoint Energy contractor, will restore the areas affected by CenterPoint Energy’s construction—typically the soft surface areas and the street. Construction will begin in the week of October 22, continue through late Fall 2018, resume in Spring 2019 and finish in Summer 2019.

In areas where pipework is completed in 2018, Q3 Contracting will work behind Michels Corporation, restoring the areas affected by Michels Corporation’s construction. If restoration is not finished in 2018 because the weather is unconducive for permanent restoration, Q3 Contracting will temporarily restore the hard and soft surfaces affected by Michels Corporation’s construction. Q3 Contracting will return in the spring and summer 2019 construction season to permanently restore these areas.

For examples of permanent and temporary restoration, please see our Restoration Practices and Updates page. 

What are the estimated traffic impacts?
  • Local businesses and residents will have access to their properties.
  • Construction will occur in segments along the construction route, rather than all at once. Lane restrictions are anticipated in areas where active construction is occurring and are necessary to keep both the public and construction personnel safe.

What is CenterPoint Energy’s mission, and how can I contact CenterPoint Energy?

At CenterPoint Energy, we are committed to providing timely and relevant information to our customers and the general public to minimize inconvenience or disruption due to our construction activities. CNP has provided safe, clean and efficient natural gas service to Minnesota communities for more than 145 years. We are proud of this record and strive to improve it by educating the public about the benefits of natural gas at CenterPointEnergy.com/BeSafe.

Frequent updates will be posted on this Project Status page. In addition, you can contact one of the following CenterPoint Energy resources:

Information Hotline:
Communication Specialist, Hannah Gullickson:
  • phone: 612-321-5546
Restoration Department:

Please reference the project name or number 86304775. We appreciate your business and look forward to continuing to serve you.