​​Project Status - St. Louis Park - Highway 100 Recon​

9/28/2015 Update

The remainder of CenterPoint Energy’s construction will be within the current closure of Minnesota Department of Transportation’s Highway 100 closure.

CenterPoint Energy understands that the Highway 100 reconstruction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

For more information on MNDOT’s current construction and closures, please click here. Thank you.​


​8/25/2015 Upda​te

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will be closing Vernon Avenue S., from Minnetonka Boulevard to 29th Street W. tomorrow, Wednesday, August 26, from 9:00 a.m. to 3:00 p.m.
 
Please anticipate the current lane shift along Minnetonka Boulevard to continue through the end of the week.
 
For more information, please continue to visit our website. Thank you. 


​8/19/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will return to the highway 100 reconstruction site tomorrow, Thursday, August 20 to complete final pipeline installation.

Crews will be working within Minnesota Department of Transportation’s current closure of Highway 100.

Within the next two, crews will move outside of the current closure and continue construction at the intersection of West Lake Street and Minnetonka Boulevard.

An additional email will be sent prior to the intersection work. For more information, please continue to visit our website. Thank you. 


4/15/2015 Update​​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe within the scope of this project.

Salem Avenue, north of Minnetonka Boulevard, will be closed to westbound traffic on Minnetonka Boulevard. Traffic will be detoured to Raleigh Avenue S. This closure will now continue until Friday, April 17th.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

4/7/2015 Update​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe within the scope of this project.

From Monday, April 13th to Wednesday, April 15th, Salem Avenue, north of Minnetonka Boulevard, will be closed to westbound traffic on Minnetonka Boulevard. Traffic will be detoured to Raleigh Avenue S.

By next Thursday, April 16th, CenterPoint Energy will be within the scope of MnDOT’s reconstruction project and closures.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.