​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​St. Peter - 4 Street N.

​​​Scheduled Start Date: Early October ​​2015​​​​

​​​​Project Description ​​​

 As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 12,250 feet of various diameter steel and plastic pipe with 8,790 feet of 2-inch and 3-inch plastic pipe along 4th Street N. and 3rd Street N. along with various cross streets.

The work will also include the replacement of approximately 120 natural gas service lines. Construction is expected to begin in early October of 2015 and will require approximately two and a half months to complete the work.