Project Status - St. Louis Park - Flag Avenue S.
5/20/2016 Update
Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue working along Flag Avenue S.
Expect a lane shift along Cedar Lake Road at Flag Avenue S. From Monday to Friday, the westbound traffic is shifted to the center turn lane.
There are currently no other major traffic restrictions, but please drive slowly in the areas of construction.
5/3/2016 Update
Crews
from Michels Corporation, an authorized CenterPoint Energy contractor, are
currently locating utilities near Flag Avenue S. today, Tuesday, May 3.
Beginning tomorrow, Wednesday, May 4,
residents and commuters along Flag Avenue S. can anticipate crews to begin
installing pipeline along the east side of the road, working from 18th Street
W. to Cedar Lake Road.
Crews anticipate reaching 22nd
Street W. by the end of the week, weather permitting.
Please be advised: the main
entrance to the Minneapolis Golf Club will be temporarily closed tomorrow for
approximately four hours as crews progress southwards.
There are currently no other
major traffic restrictions, but please drive slowly in the areas of
construction.