9/6/2016 Update

Crews from CenterPoint Energy finished construction on the natural gas distribution main along Eagle Creek Boulevard in Shakopee. The project began on August 1 and ended on August 15, involving the installation of the main and the restoration of the hard and soft surfaces.

For more questions or information, please contact our Information Hotline at 612-321-5369 or our Communication Specialist, Hannah Gullickson, at 612-321-5546.​


8/4/2016 Update

Crews from Michels Corporation, an authorized contractor from CenterPoint Energy, will be installing approximately 1,282 feet of 4-inch plastic gas pipeline along County Road 101 near the intersection of W. 70th Street in Shakopee.