​Project Status - Savage - Credit River

7/22/2015 Update

Crews from Q3, an authorized CenterPoint Energy contractor, finished soft surface restoration within the scope of the Credit River construction project. Hard surface restoration will begin the week of July 27.

We understand that the Credit River construction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we work to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042 or visit our website. Thank you.


7/9/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of this project.

Crews anticipate completing hard and soft surface restoration by next Friday, July 17.

If you have questions regarding CenterPoint Energy's restoration, please call 612-321-5042 or visit our website.

Please visit our website for more information. Thank you. ​

7/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish installing natural gas distribution pipe near Credit River today, Wednesday, July 1st.

Machinery removal and site clean-up will take place tomorrow.

Please anticipate 144th Street W. and Monterey Avenue S. to remain closed until restoration takes place early next week.

Thank you for your patience during CenterPoint Energy's construction project.

Please visit our website again for the final restoration update. ​

6/23/2015 Update​​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, started installing natural gas distribution pipe near Credit River yesterday, Monday, June 22nd.

Machinery is now set up along 144th Street W. and Monterey Avenue S. This road will be closed for the duration of the construction project. Please follow the posted detour.

On Monday, June 29th, Joppa Avenue S. will be closed for one day. Please follow the posted detour as seen below.

Construction within the scope of is anticipated to continue for the next three weeks.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​​