​12/11/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished construction and temporary restoration within the scope of the County Road 47 project.

We understand that the County Road 47 construction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete all possible restoration in the 2015 construction season.

In the spring, crews will return onsite to complete final restoration. For inquiries or concerns, please call our hotline number at 612-321-5042 or visit our website.

Even though CenterPoint Energy's 2015 construction season will be coming to a close at the end of the month, please continue to visit our website during the off season as 2016 projects will be added weekly! Thank you.

 ​

11/19/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe from just west of Lawndale Lane N. to just east of Elm Creek.

Please anticipate County Road 47 to be reduced to a single lane from Lawndale Lane N. to Dunkirk Lane N. as crews continue installing pipeline westwards. Flaggers will be directing traffic from 7:00 a.m. to approximately 4:00 p.m. through Saturday, November 21.

On Monday, November 23, please anticipate flaggers at the intersection of Lawndale Lane N. and County Road 47.

Due to the cold weather, crews from Q3, an authorized CenterPoint Energy contractor, will hydromulch all soft surface areas for erosion control over the winter. In the spring, crews will return onsite to complete final restoration.

Crews anticipate completing construction along County Road 47 before Thanksgiving. For more information, please visit our website. Thank you. ​​
 ​


11/12/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe along County Road 47, from Lawndale Lane N. to Troy Lane N.

O
n Monday, November 16, crews will install the final portion of pipeline from just west of Lawndale Lane N. to just east of Elm Creek.

Crews anticipate working for approximately three days next week, weather permitting.

Please drive slowly and with caution in the areas of construction.

Restoration will follow shortly. For more information, please visit our website.
Thank you. ​​



11/5/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will continue installing natural gas distribution pipe along County Road 47 through Monday, November 9.

Crews are currently installing natural gas distribution pipe along the south shoulder of County Road 47, working westwards from just west of Lawndale Lane N. to Troy Lane N.

Please drive slowly and with caution in the areas of construction.

Restoration will follow in the coming weeks. For more information, please visit our website. Thank you. ​


10/14/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe along County Road 47 on Friday, October 16.

Crews will be onsite setting up traffic control signs tomorrow, Thursday, October 15.

Crews will begin construction along the south side of County Road 47, working westwards from Dunkirk Lane N. to Troy Lane N.

Flaggers will be onsite Monday, October 19 directing westbound and eastbound traffic. Please drive with caution in the areas of construction.

Please anticipate construction along County Road 47 to continue for approximately one and a half weeks, weather permitting. Thank you. 
​​​