​​​​Project Status - Osseo - 2nd Street E. 

7/22/2015 Update

Crews from Q3, an authorized CenterPoint Energy contractor, have finished restoration within the scope of the 2nd Street E. area construction project.

We understand that the 2nd Street E. area construction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy's restoration, please call 612-321-5042. Thank you.​

6/10/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish replacing service lines within the scope of the 2nd Street E. construction project in Osseo by early next week.

Representatives from CenterPoint Energy will contact the remaining residents whose gas service may be affected to schedule the necessary construction work on their property.

Hard surface restoration is underway. Soft surface restoration will soon follow.

We thank you for your patience as construction wraps up and restoration begins. For more information, please visit our website. Thank you.​

6/3/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution within the scope of the 2nd Street E. construction project.

Crews completed replacing service lines along 2nd Avenue SE and 3rd Avenue SE.

One crew is currently replacing service lines at the intersection of 93rd Avenue N. and 2nd Avenue NW and working in a southeast direction.

The second crew is currently replacing service lines at the intersection of 2nd Street SE and 8th Avenue SE and working in a southwest direction.

Please note service line replacements will follow. Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Service line replacements are anticipated to continue for the next three weeks. Please continue to visit our website to receive project updates and restoration updates. Thank you.​

5/21/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution within the northwest area of construction.

Crews are currently installing natural gas distribution pipe along 6th Avenue SE, 7th Avenue SE and 8th Avenue SE. Crews anticipate finishing these streets by early next week.

Installation of natural gas distribution pipe is approximately 70% complete. Crews anticipate  finishing all streets by the end of next week.

Please note service line replacements will follow. Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​

5/10/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution along 2nd Avenue NW.

Crews will begin installing natural gas distribution pipe along 1st Avenue NW and 3rd Street NE tomorrow, Monday, April 11. Construction will continue for approximately one week in this area.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

4/29/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe today, Wednesday, April 29th in Osseo.

Construction is underway along the following location:

  • 2nd Avenue SE, from 1st Street SE to 2nd Street SE
  • 3rd Avenue SE, from 2nd Street SE to County Road 81
  • 7th Avenue SE, from 3rd Street NE to 2nd Street NE

Construction will continue for approximately 1.5 weeks in this area.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​