Project Status - Mound - Tuxedo Boulevard
Construction is finished in Mound on Tuxedo Boulevard.
6/21/2016 Update
Crews from CenterPoint Energy have finished installing the gas pipeline under Tuxedo Boulevard. Service work is completed and the old main pipeline has been abandoned.
Restoration of the blacktop road will be coordinated with the upcoming city work.
CenterPoint Energy thanks the residents for their patience. Thank you.
6/7/2016 Update
Last week, crews from
CenterPoint Energy finished boring on Tuxedo Boulevard under the sidewalk and
started on the road crossing tie-ins.
This week crews are boring
southward on Wilshire Boulevard (County Road 125) which may slow traffic, but
no detours should be necessary. They are currently halfway through Wilshire.
After Wilshire crews will be
boring on a road crossing on Pelican Point Circle. Any remaining work will
involve final touches.