​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Minnetonka - Shady Oak Road (County Road 61)

​​​Scheduled Start Date: August 22, 2016

​​​​Project Description ​​​

For a system improvement job, crews from Michels Corporation, an authorized contractor for CenterPoint Energy, will be installing about 1,600 feet of 6-inch natural gas pipe and connecting about 25 gas services to the new main pipe in Minnetonka. 

The upgraded pipe will be installed along the northeastern side of Shady Oak Road (County Road 61) from Aspen Ridge Drive to Plymouth Road past Orchard Lane. (See map for detail.) Construction is expected to begin on Monday, August 22, 2016, and will last until approximately the week of October 3, 2016.