​​​Minneapolis - Waite Park Concrete Rehabilitation

Scheduled Start Date: Late April or Early May 2018

Project Description

What is CenterPoint Energy doing for construction?

Crews from CenterPoint Energy will begin replacing an existing natural gas pipeline in Minneapolis in late April or early May 2018. Project construction is expected to last until August 2018. (Frequent updates will be posted on the Project Status page below.) Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas mains along the following streets (see map below):

  • 36th Avenue NE from Johnson Street NE to Cleveland Street NE
  • 35th Avenue NE from Johnson Street NE to Ulysses Street NE
  • Ulysses Street NE from 33rd Avenue NE to 35th Avenue NE
  • Hayes Street NE from 34th Avenue NE to 36th Avenue NE
  • Wilshire Place NE from 34th Avenue NE to 36th Avenue NE
  • Garfield Street NE from 33rd Avenue NE to 36th Avenue NE
  • Arth​ur Street NE from 33rd Avenue NE to 34th Avenue NE

This project will be done in coordination with the City of Minneapolis’s “Waite Park Neighborhood Concrete Street Rehabilitation​” project, which began in 2017 and will resume in Spring 2018. For more information on their project, please visit their website.

Lane restrictions are anticipated in areas where active construction is occurring. The lane restrictions are necessary to keep both the public and construction personnel safe.

Construction will happen in three phases:

  • Phase 1 is installing the natural gas distribution main.
  • Phase 2 is connecting the natural gas service lines to the new main along the same construction route. (A gas service line is a small-diameter pipe connecting the customer's gas service to the main line in the street.)
  • Phase 3 is restoring the areas affected by construction--typically the utility easement, the street, and the customer's yard.

How may construction affect customers?

As part of this main project, the crews will also be replacing several natural gas service lines that connect from the main to the customer's property. Customers will experience a short disruption of gas service as the crews are installing the gas service line. 

Crews may have to dig in the ground on your property in the utility easement to complete the task of service and main distribution line replacement. If a customer’s property is disturbed, CenterPoint Energy will restore the hard and soft surfaces affected by construction at no cost to you.

How can I contact CenterPoint Energy?

For questions about the project, please call our Information Hotline at 612-321-5369 or our Communication Specialist at 612-321-5546. For questions about restoration (hard or soft surfaces) please call our Restoration Department at 612-321-5042. CenterPoint Energy wants to thank you for your patience.