​​​​​​​​Minneapolis - Main Street NE​​​​  

​​​Scheduled Start Date: September 19, 2016

​​​​Project Description​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 1,759 feet of various diameter plastic and steel pipe with 2,009 feet of 2-inch and 8-inch plastic pipe along Main Street NE, from just north of 8th Avenue NE to 5th Avenue NE.  

The work will also include the replacement of approximately 35 natural gas service lines. Phase 1 of construction started on September 28, 2015, and ended on December 1, 2015. Phase 2 of construction is expected to begin in September 19, 2016, and will last until approximately the end of November 2016