​​Project Status Update - Minneapolis - Harriet Avenue S.

12/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of the Harriet Avenue S. project yesterday, Monday, November 30.

Crews will begin service line replacements today, Tuesday, December 1 at scattered locations along Harriet Avenue S. Crews anticipate service line replacements to continue for the next one to one and a half weeks.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property. If the gas meter is located inside your home or building, we will move it to an outside location.

Due to the cold weather, crews from Q3, an authorized CenterPoint Energy contractor, will hydromulch all soft surface areas for erosion control over the winter and blacktop any needed restoration on the street and sidewalks. In the spring, crews will return onsite to complete final restoration.

For more information, please visit our website. Thank you.​​
 ​


11/25/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe along the east side of Harriet Avenue S., from 56th Street W. to 55th Street W.

In addition to Harriet Avenue S., crews also installed natural gas distribution pipe along 56th Street W., from Harriet Avenue S. to Grand Avenue S.

Crews anticipate completing final pipeline installation by the end of the day today, Wednesday, November 25.

On Monday, November 30, crews will begin replacing natural gas service lines. Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property. If the gas meter is located inside your home or building, we will move it to an outside location.

Please anticipate no parking signs to remain onsite tomorrow, Thanksgiving Day and Friday, November 27. However, parking will be allowed and permitted over these next two days despite the current signage.

For more information, please visit our website. Thank you.​​

 

11/19/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will be moving equipment onsite in preparation for the Harriet Avenue S. project beginning tomorrow, Friday, November 20.

Residents can anticipate crews to begin installing natural gas distribution pipe northwards along the east side of Harriet Avenue S., from 56th Street W. to 55th Street W. on Monday, November 23.

Please anticipate no parking along the east side of Harriet Avenue S. in the areas of construction.

Construction will continue for the next two and a half weeks, weather permitting.

For more information, please visit our website. Thank you.​

​​​