​​​​​​Project Status - Minneapolis - Franklin Avenue SE

Construction is finished in Minneapolis on Franklin Avenue SE.

6/10/2016 Update

​Crews from CenterPoint Energy have finished replacing the gas pipeline on Franklin Avenue SE. They will soon begin restoring the blacktop road.


6/7/2016 Update

Construction is scheduled to be complete along Franklin Avenue SE. by the week of Tuesday, June 7. By then crews should finish replacing gas services along Franklin and Cecil Street SE.

5/20/2016 Update

Crews continue work along Franklin Avenue SE and will be working from Cecil Street SE to Emerald Street SE.  Please note that there will be no parking along Cecil Street SE from Franklin Avenue SE to Sharon Avenue SE Monday to Friday from 7 a.m. to 6 p.m.


5/16/2016 Update

From Friday, May 13 through Wednesday, May 18 the south sidewalk and parking lane will be closed along Franklin Avenue from Bedford Street SE to Emerald Street SE.


5/3/2016 Update

Beginning tomorrow, Wednesday, May 4, residents and commuters along Franklin Avenue SE can anticipate crews to begin installing pipeline along the south side of Franklin Avenue SE, working from just west of Malcolm Avenue SE to Cecil Street SE.

Please anticipate the southern parking lane and sidewalk to be closed through Tuesday, May 10.

From Tuesday, May 10 through Tuesday, May 17, the northern parking lane and sidewalk will be closed from Malcolm Avenue SE to Cecil Street SE along Franklin Avenue SE.

The sidewalk will reopen every day at 5:00 p.m.

CenterPoint Energy thanks you for your patience as construction begins along Franklin Avenue SE. Thank you.​​