​​​​​​​​​​​​​​​​​​​​​​​Minneapolis - Emerson Avenue S.

​​​Scheduled Start Date: September 2015​​​​

​​​​Project Description ​​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy ​​contractor, will replace approximately 1,365 feet of various steel and plastic pipe with 2,681 feet of 2-inch, 6-inch and 8-inch plastic pipe and 20-inch steel pipe along Emerson Avenue S., from Douglas Avenue to Franklin Avenue W. The work will also include replacing approximately 40 natural gas service lines. Construction is expected to start September of 2015 and will require approximately two months to complete the work.​

Please anticipate a full road closure of Emerson Avenue S. beginning Monday, November 9. Traffic will be open to local residents only.