​​​​​​​​​Brooklyn Center/Minneapolis - Bryant Avenue N. ​​

Scheduled Start Date: Completed​


Project Description ​​​​

For a city of Minneapolis paving project​, Michels Corporation, an authorized CenterPoint Energy contracto​r, replaced approximately 5,360 feet of small diameter steel and plastic pipe with approximately 5,257 feet of 2-inch plastic pipe along Bryant Avenue N​., from 53rd Avenue N. to 45th Avenue N.

The work included the replacement of approximately 180 natural gas service lines. Construction began the week of March 28, 2016 and has been completed in June 2016. For more details, see Project Status below.