​​​​​​​​​​​​​​​​​​​​​​​​​​​Minneapolis - Anderson United Community School

​​​Scheduled Start Date: Monday, July 27, 2015​​​​

​​​​Project Description ​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 800 feet of 24-inch steel pipe with 1000 feet of 24-inch steel pipe as well as some minor replacement of smaller diameter pipe.

Construction will occur along Anderson Lane, from 10 Avenue S. to 12 Avenue S. and along 12 Avenue S., from Anderson Lane to 27 Street E. A short section of work will also take place north of Anderson School, along 27 Street E (see map below for detail).

Construction is expected to begin the week of July 27, 2015 and will require approximately one month to complete the work. Please anticipate traffic delays and potential lane closures as construction progresses.

More Project Resources​

​​​​​​