​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Minneapolis - 8th Street S.

​​​Scheduled Start Date: March 28, 2016​​​​

​​​​Project Description ​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 4,964 feet of various diameter steel pipe with approximately 4,102 feet of 16-inch steel pipe and approximately 1,170 feet of 2-inch plastic pipe along 8th Street S., from 13th Avenue S. to 3rd Avenue S. (see map below fo​r detail).
​​
The work will also include the replacement of 15 natural gas service lines. ​Construction is expected to start on Monday, March 28, 2016 and will continue through August.  

Please be aware that in addition to CenterPoint Energy, RJM Construction, Mortenson Construction and Kraus-Anderson Construction are also working along 8th Street S.