​​​​​​​​Minneapolis - 50th Street W. and Xerxes Avenue S. 

​​​Scheduled Start Date: Spring 2016

​​​​Project Description ​​​​

As a system upgrade ​​​project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 9,236 feet of various diameter steel and plastic pipe with approximately 8,335 feet of 2-inch and 4-inch plastic pipe along 50th Street W., from ​​Ewing Avenue S. to Upton Avenue S. and along Xerxes Avenue S., from 54th Street W. to 47th street W. (see map below for detail). 

The work will also include replacing approximately 75 natural gas service lines. Construction is expected to begin in the spring of 2016 and will require approximately three and a half months to complete the work.