11/5/2015 Update

Crews from Q3, an authorized CenterPoint Energy contractor, finished restoration along 34th Avenue S. and 52nd Street E.


We understand that the 34th Avenue S. construction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy's restoration, please call 612-321-5042 or visit our website.

Interested in receiving updates for other CenterPoint Energy construction projects near you? Click here to view all current or upcoming CenterPoint Energy construction projects. Thank you. ​


​10/21/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished replacing service lines along 52nd Street E. earlier this week.

Crews from Q3, an authorized CenterPoint Energy contractor, are currently restoring the sidewalk, street and yards along 34th Avenue S. and 52nd Street E.

We understand that the 34
th Avenue S. construction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we work to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy's 
restoration, please call 612-321-5042 or visit our main website. Thank you.


10/13/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish replacing service lines along 52nd Street E. on Thursday, October 15.

Crews from Q3, an authorized CenterPoint Energy contractor, are currently restoring the sidewalk, street and yards along 34th Avenue S.

Please anticipate an additional email to follow in the coming weeks with final restoration details.

For more information, please visit our website. Thank you.​


10/6/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish service line replacements along 34th Avenue S. tomorrow, Wednesday, October 7.

Crews will then begin replacing service lines along 52nd Street E. Please anticipate no parking on either side of 52nd Street E. through mid to late October.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please continue to visit our website for future updates. Thank you.​


 9/23/2015 Update
Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe along 34th Avenue S. and 52nd Street E.

Crews replacing service lines along 34th Avenue S. anticipate continuing through next Friday, October 2.

In early October, crews will begin replacing service lines along 52nd Street E. Service line replacements along 52nd Street E. will continue through mid to late October.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please anticipate intermittent no parking and sidewalk closures along 34th Avenue S. and 52nd Street E. as service line replacements continue

Please continue to visit our website for future updates. Thank you.​


​​9/16/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently installing natural gas distribution pipe along the east side of the 34th Avenue S. and Keewaydin Place intersection.

On Friday, September 18, crews will begin replacing service lines, working south to north.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property. Please note crews will also be working Saturdays in this area.

Please anticipate intermittent no parking and sidewalk closures along 34th Avenue S. as service line replacements begin.

For more information, please visit our website. Thank you.   


9/11/2015 Update ​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe along 52nd Street E., between 31st Avenue S. and 34th Avenue S.

C
rews are currently installing natural gas distribution pipe northwards along the east side of 34th Avenue S. near 53rd Street E.

C
rews anticipate working between 53rd Street E. and 51st Street E. through Thursday, September 17.​

Please anticipate no parking and sidewalk closures along the east side of 34th Avenue S. in two block increments as construction progresses.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.  


9/4/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas pipeline along 34th Avenue S. on Tuesday, September 8.

Crews will begin installing natural gas distribution pipe just north of the intersection of 34th Avenue S. and 54th Street E. and will continue working northwards along the east side of 34th Avenue S. Crews anticipate completing the first block, from 54th Street E. to 53rd Street E., by next Thursday, September 10.

Please anticipate intermittent lane shifts, no parking and sidewalk closures along the east side of 34th Avenue S. in two block segments as construction progresses.