​​​Minneapolis - 34​th Avenue S. 

​​​Scheduled Start Date: September 3, ​​2015​​​​

​​​​Project Description ​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy ​​contractor, will replace approximately 2,430 feet of 8-inch steel pipe with 3,680 feet of 2-inch and 3-inch plastic pipe along 34th Avenue S., from 54th Street E. to Keewaydin Place and along 52nd Street E., from 31st Avenue S. to 34th Avenue S. The work will also include replacing approximately 90 natural gas service lines. Construction is expected to start in the Fall of 2015 and will require approximately two months to complete the work.​ 