​Project Status - Minneapolis - 26th Avenue N.

10/19/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished construction within the scope of the 26th Avenue N. construction project.

Crews from Q3, an authorized CenterPoint Energy contractor, will finish restoration tomorrow, Tuesday, October 20.

We understand that 26th Avenue N. construction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we work to complete restoration as safely and quickly as possible.

Please note the City of Minneapolis’ 26th Avenue N. Paving/Renovation project is underway.

If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042. Thank you.


​10/5/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will complete construction within the scope of this project by the end of the week.

Please anticipate the following through the remainder of the week:

  • 26th Avenue N., west of West Broadway Avenue, will be closed.
  • Westbound 26th Avenue N. traffic, east of West Broadway Avenue, is closed.
  • Eastbound 26th Avenue N. traffic, east of West Broadway Avenue, will remain open.
  • The intersection of Sheridan Avenue N. and 26th Avenue N. is closed.
  • Northbound and southbound West Broadway Avenue traffic is reduced to one lane in each direction near 26th Avenue N. 

Please continue to visit our website for more information. Thank you.

​9/23/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas pipe near the intersection along 26th Avenue N.

All lanes along West Broadway Avenue, near 26th Avenue N., are now open.

The intersection of Sheridan Avenue N. and 26th Avenue N. will remain closed through September 30.

One westbound 26th Avenue N., east of West Broadway, remains open.

Traffic within the scope of the 26th Avenue N. project is anticipated to return to normal on Wednesday, September 30. Please anticipate this schedule to change permitting potential construction changes.

Please continue to visit our website for more information. Thank you. 


9/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas pipe near the intersection of West Broadway Avenue and 26th Avenue N.
 
The two eastern lanes of northbound West Broadway Avenue, near 26th Avenue N., will remain closed through Friday.
 
Please anticipate potential delays on northbound West Broadway Avenue as it will be reduced to one lane in each direction.
 
From Tuesday, September 8 to Friday, September 11, the two western lanes of southbound West Broadway Avenue will be closed.
 
Sheridan Avenue N., 250 feet south of 26th Avenue N., will remain closed through September 30.
 
Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you. ​


8/14/2015 Update

 Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin construction along 26th Avenue N. and Sheridan Avenue N. on Monday, July 17.

On Monday, July 17, Sheridan Avenue N., 250 feet south of 26th Avenue N., will be closed for approximately one month.

Please anticipate lane shifts along West Broadway Avenue and 26th Avenue N. through next Friday, August 21.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.


4/22/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue construction along Aldrich Avenue N., from 25th Avenue N. to 26th Avenue N.

Aldrich Avenue N., from 25th Avenue N. to 26th Avenue N. will continue to remain closed until approximately Friday, May 1st. Restoration will follow in this area.

Please follow the posted detour to either Lyndale Avenue N. or Bryant Avenue N. For more information, please visit our website. Thank you.​

4/3/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin construction along Aldrich Avenue N., from 25th Avenue N. to 26th Avenue N. on Monday, April 6th.

Aldrich Avenue  N., from 25th Avenue N. to 26th Avenue N. will be closed for the next seven weeks. Please  follow the detour to either Lyndale Avenue N. or Bryant Avenue N.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

9/18/2014 Update

Restoration within the scope of this project will be completed by the end of the week.

CenterPoint Energy understands that construction activity of this sort can be an inconvenience to people living, working and/or commuting in and around the area, so we greatly appreciate your patience and understanding as we continue to complete restoration as safely and quickly as possible.

If you have any questions regarding restoration, please call 612-321-5042. Thank you.​

9/4/2014 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish construction on 26th Avenue N. by the beginning of next week. Restoration will follow construction.

CenterPoint Energy understands that construction activity of this sort can be an inconvenience to people living, working and/or commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

If you have any questions regarding restoration, please call 612-321-5042. Thank you.

8/13/2014 Update

Michels Corporation, an authorized CenterPoint Energy contractor, will continue construction on 26th Avenue N. For the next three weeks, crews will be working from Lyndale Avenue S. to 3rd Street N. on 26th Avenue N. The road will be closed in this area as construction progresses.

Service line replacements within the scope of this project will be completed by today, Wednesday, August 13th.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

8/5/2014 Update

Michels Corporation, an authorized CenterPoint Energy contractor, will finish replacing natural gas distribution pipe on 26th Avenue N. by the end of the week. Crews are currently working at the intersections of 6th Street N. and 26th Avenue N. and 3rd Street N. and 26th Street N.

Crews are replacing service lines between 3rd Street N. and 5th Street N. on 26th Avenue N.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.​

7/23/2014 Update

Michels Corporation, an authorized CenterPoint Energy contractor, will continue replacing natural gas distribution pipe on the south side of 26th Avenue N., from Lyndale Avenue N. to I-94.

The south lane of eastbound 26th Avenue N. will be closed for approximately three more days.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

7/17/2014 Update

Michels Corporation, an authorized CenterPoint Energy contractor, will begin replacing natural gas distribution pipe on the south side of 26th Avenue N., from Lyndale Avenue N. to I-94 on Monday, July 21st.

The south lane of eastbound 26th Avenue N. will be closed during construction for approximately three weeks, weather permitting.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.​​​