​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Maple Grove - Fernbrook Lane

​​​Scheduled Start Date: Summer 2015​​​​​

​​​​Project Decription ​​​​

In preparation for the Highway 610 extension project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 850 feet of 8-inch steel pipe along Fernbrook Lane and 4-inch plastic pipe across the new highway 610 at Ranchview Lane. Construction is expected to begin in summer 2015 and will require approximately three weeks to complete the work.

For more information, please visit Minnesota's DOT.​