​​​​Project Status - Lakeville - Griffon Trail​

​5/5/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished all construction within the scope of this project!

We appreciate your patience and understanding as CenterPoint Energy crews wrap up construction in the area today, Thursday, May 5. Thank you.


4/18/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently installing pipeline along various streets south of Griffon Trail. Crews anticipate working through the end of the week in this area.

A second CenterPoint Energy crew is currently working on service line replacements along various streets north of Griffon Trail. If the gas meter is located inside your home or building, we will move it to an outside location.

After crews complete all service line replacements for homes located north of Griffon Trail, they will move to the south side of the project.


4/6/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, completed installing natural gas pipeline within the first phase of construction in Lakeville.

Please anticipate crews to begin installing pipeline along Griffon Trail tomorrow, Thursday, April 7.

Crews will install pipeline along the south side of Griffon Trail, working westwards from Cedar Avenue to Grinnell Avenue. Crews anticipate working along Griffon Trail through the following Wednesday or Thursday.

Residents can also anticipate representatives from CenterPoint Energy to continue working on service line replacements at scattered locations throughout the scope of the project. If the gas meter is located inside your home or building, we will move it to an outside location.

For more information, please visit our website. Thank you.

 

3/27/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing pipeline within the northeast project area tomorrow, Monday, March 28.

Crews will first install pipeline along Goodview Circle. Crews will then work their way eastwards and install pipeline along the south side of Godson Circle and along both sides of Godson Drive.

Crews will finish the first phase by installing pipeline along the south side of Glen Oaks Court and the east side of Glen Oaks Road.

Crews anticipate working within the first phase for the entire week.

For more information, please visit our website. Thank you.​