12/11/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finished construction and temporary restoration within the scope of the 6th Street S. project.

We understand that the 6th Street S. construction project was an inconvenience to people living, working and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete all possible restoration in the 2015 construction season.

In the spring, crews will return onsite to complete final restoration. For inquiries or concerns, please call our hotline number at 612-321-5042 or visit our 
website.

Even though CenterPoint Energy's 2015 construction season will be coming to a close at the end of the month, please continue to visit our website during the off season as 
2016 projects will be added weekly! Thank you. ​

12/2/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish replacing service lines within the scope of the 6th Street S. project tomorrow, Thursday, December 3.

Representatives from CenterPoint Energy will continue to contact the final residents whose gas service may be affected to schedule the necessary construction work on their property.

Due to the cold weather, crews from Q3, an authorized CenterPoint Energy contractor, will hydromulch all soft surface areas for erosion control over the winter and blacktop any needed restoration on the street and sidewalks. In the spring, crews will return onsite to complete final restoration. For inquiries or concerns, please call our hotline number at 612-321-5042 or visit our restoration website.

For more information, please visit our website. Thank you.​


11/23/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of this project last week.

Crews are currently replacing service lines at scattered locations along 10th Avenue S.

Representatives from CenterPoint Energy will continue to contact residents along 6th Street S., 8th Avenue S. and 7th Avenue S. whose gas service may be affected to schedule the necessary construction work on their property.

Residents can anticipate crews working at scattered locations as appointments are made through Friday, December 4.

Please continue to visit our website for more information. Thank you.  ​
 ​

11/16/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe along 6th Street S. last week.

Crews are currently installing the second half of pipeline along the west side of 10th Avenue S. After crews complete 10th Avenue S., construction along 8th Avenue S. will begin. Crews anticipate installing natural gas distribution through the end of the week.

On Wednesday, November 18, crews will begin replacing service lines along 6th Street S.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property. Service line replacements are anticipated to continue for the next two weeks.

Please continue to visit our website for more information. Thank you.  ​


11/11/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently onsite locating utilities in preparation for the start of tomorrow’s construction.

T
omorrow, Thursday, November 12, crews will begin installing natural gas distribution pipe along the south side of 6th Street S.

Early next week, crews will install natural gas distribution pipe along the west side of 8th Avenue S. and 10th Avenue S.

Crew anticipate installing natural gas distribution through the end of next week, weather permitting. Service line replacements will follow.