​​​​​​​Project Status - Golden Valley - Winnetka Avenue N. 

​9/9/2015 Update

Crews from Q3, an authorized CenterPoint Energy contractor, completed restoration within the scope of the Winnetka Avenue N. construction project.

We understand that the Winnetka Avenue N. construction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy's restoration, please call 612-321-5042. Thank you. 

​​​​8/24/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished replacing service lines within the scope of the Winnetka Avenue N. construction project last Friday, August 21.

Crews from Q3, an authorized CenterPoint Energy contractor, will begin restoration shortly.

Please anticipate the final restoration update to follow in September. Thank you. 


​8/11/2015 Update

 

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish installing natural gas distribution pipe Winnetka Avenue N. tomorrow, Wednesday, August 12.

Crews continue replacing natural gas services lines northwards along Winnetka Avenue N. and are currently working near Plymouth Avenue N.

Crews anticipate replacing five service lines per day and will continue working through September.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you. 


 

7/31/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe northwards along the west side of Winnetka Avenue N.

Today, crews anticipate completing construction at the intersection of Plymouth Avenue N. and Winnetka Avenue N. and temporarily restore any hard surface patches as needed.

The western lane of southbound Winnetka Avenue N. will remain closed as crews continue construction north of Plymouth Avenue N. Please anticipate potential delays on southbound Winnetka Avenue N. as it will be reduced to one lane.

On Monday, August 3, crews will begin replacing service lines near Winnetka Avenue N. and Orkla Drive.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​


 

7/21/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, started installing natural gas distribution pipe at the intersection of Orkla Drive and Winnetka Avenue N.

Crews will be working northwards along the west side of Winnetka Avenue N. toward 23
rd Avenue N.

The western lane of southbound Winnetka Avenue N. is closed between Orlka Drive and Olympia Street.

Please anticipate potential delays on southbound Winnetka Avenue N. as it will be reduced to one lane.

Crews anticipate installing natural gas distribution pipe for the next six weeks along Winnetka Avenue N.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

 

​ 

​​​​