​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Golden Valley - ​Winnetka Avenue N.  

​​​Scheduled Start Date: Late July 2015 ​​​​​​

​​​​Project Description ​​​

In preparation for a Hennepin County paving project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately 5,000 feet of various diameter steel ​pipe with 5,200 feet of various diameter plastic pipe along Winnetka Avenue N., from 23rd Avenue N. to Orkla Dr. (see map below for detail).

Construction is expected to begin the week of July 20th, 2015 and require approximately one and a  half months tcomplete the work. Approximatley 100 service lines will be replaced. Please anticipate traffic delays and potential lane closures as construction progresses. 

 