​​​​​​Fridley - Fridley Reconstruction

​​​Scheduled Start Date: March 2015​​​​

​​​​Project Decription ​​​​

In preparation for the city of Fridley’s mill and overlay project, Michels Corporation, an authorized CenterPoint Energy contractor, will replace approximately two miles of small diameter pipe with 2-inch plastic pipe within the neighborhood that extends from 49th Avenue NE to I-694 and between Main Street NE and University Avenue NE (see map for detail). The work will also include replacing approximately 208 natural gas service lines. Construction is anticipated to start March 30th, 2015 and require approximately three months to complete the work.​