7/9/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished construction within the scope of the Fridley reconstruction project last Thursday, July 2.

We understand that the Fridley reconstruction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we begin restoration.

If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042 or visit our website. Thank you.
 

6/19/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of this project.
Service line replacements continue along various streets within the Fridley Reconstruction project.

Crews anticipate completing all service line replacements, with the exception of 53rd Avenue NE by early next week.

Crews will begin replacing service lines along 53rd Avenue NE on Monday, June 22nd. Construction along this street will continue until approximately Wednesday, July 1st.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you. 

4/24/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of this project.
Service line replacements are completed or near completion along the following locations:

  • Altura Road NE
  • Horizon Circle NE
  • Horizon Drive NE, south of 53rd Avenue NE – one service line replacement remains
  • Topper Circle – two service line replacements remain

Beginning Monday, April 27th, service line replacements will begin along Clearview Street NE.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you. 

4/14/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish installing natural gas distribution pipe within the scope of this project by the end of the day tomorrow.

Blacktop restoration is underway along Main Street NE. The lane shift at the intersections of Main Street NE at Pilot Avenue NE and at Panorama Avenue NE will be removed after restoration.

Service line replacements are underway along the following locations:

  • Horizon Circle NE – one service line replacement remains
  • Horizon Drive NE, south of 53rd Avenue NE
  • 3rd Street NE, from 49th Avenue NE to Panorama Avenue NE

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

4/9/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution at the intersection of Altura Road NE and 53rd Avenue NE. There will be a lane shift along 53rd Avenue NE as construction continues. Blacktop restoration of this intersection will occur early next week.

Beginning Monday, April 13th, crews will be working at the intersections of Main Street NE at Pilot Avenue NE and at Panorama Avenue NE. Two-way traffic will be maintained in these areas with a lane shift at the intersections. Blacktop restoration will occur in this area the following day.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

3/27/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe on Monday, March 30th in Fridley.

Construction will begin along the east side of Altura Road NE, from Horizon Drive NE to 53rd Avenue NE. Construction will continue for three days in this area.

Construction will also begin along 3rd Street NE, from Horizon Drive NE to 49th Avenue NE.

Two-way traffic will be maintained in these areas with potential lane shifts at the intersections.

Construction within the scope of this project is expected to be completed by late April. Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​