Project Status - Edina - Valley View Road​

7/15/2015

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, have finished construction and restoration within the scope of the Arden Park construction project.

W
e understand that the Arden Park construction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042 or visit our website. Thank you. ​


6/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently replacing natural gas distribution pipe along Valley View Road, west of Sally Lane.

Crews will finish installing natural gas distribution pipe and replacing service lines within the scope of CenterPoint Energy’s construction project by Friday, June 5th.

Representatives from CenterPoint Energy will contact the remaining five residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​

5/20/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe and service line replacements yesterday along Comanche Court.

Approximately 17 service line replacements are also complete along Valley View Road.

Due to congestion with city reconstruction crews, CenterPoint Energy will be moving offsite until next Tuesday, May 26th.

On Tuesday, crews will begin installing natural gas distribution pipe along Braemar Boulevard.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​

5/13/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe and replacing service lines today, Wednesday, May 13th in Edina.

Crews will begin construction along Comanche Court. Construction will continue until Saturday, weather permitting.

Crews will then move to Valley View Road next week.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​