​​Project Status - Edina - Tracy Avenue Roundabout 

Construction is finished in Edina on the Tracy Avenue Roundabout.

7/29/2016 Update

Crews from CenterPoint Energy have finished construction on the Tracy Avenue Roundabout in Edina. Phases I and II, including the installation of the main gas pipeline, services and restorations, are completed. 

CenterPoint Energy wants to thank you for your patience.​



6/23/2016 Update

For a City of Edina construction project​, crews from CenterPoint Energy are working at the Tracy Avenue and Valley View Road roundabout.

At the intersection of Tracy Avenue and Valley Lane in Edina, Phase I is complete. The main pipeline has been installed. Crews will return to Tracy Avenue later in the summer to complete Phase II.

CenterPoint Energy wants to thank you for your patience.



​5/3/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently done installing natural gas pipeline along Valley View Road.

Once the City of Edina begins construction at the roundabout, CenterPoint Energy crews will return onsite to complete final construction.​ Thank you.


4/11/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas pipeline along the west side of Valley View Road today, Monday April 11.

Please anticipate lane shifts along the west side of Valley View Road, from 66th Street W. to Valley Lane for the next two to three weeks.

Construction is anticipated to continue for the next three weeks. Please note that after CenterPoint Energy completes construction, the City of Edina will begin construction of the roundabout.

Two-way traffic will be maintained in this area but please drive slowly and with caution in the areas of construction. Thank you.