10/3/2023

CenterPoint Energy’s authorized contractors are finishing CenterPoint Energy’s gas line replacement project in the Rolling Green Neighborhood in Edina. While Michels Corporation finished the natural gas work (including replacing the mains, moving inside meters outside by appointment, and replacing and/or reconnecting the service lines to the new mains), Q3 Contracting has been following to restore the areas affected by Michels Corporation’s work.


On boulevards and lawns, they will refill the areas with black dirt, grass seed, and netting that degrades over about four months. Prior to mowing the restored area, remove any loose staples that secured the netting.


We thank you for your patience as we upgraded our natural gas infrastructure. We wish you a great season!

8/7/2023

From Monday, August 7 to Thursday, August 24, a crew from Michels Corporation, CenterPoint Energy’s authorized contractor, is scheduled to replace the natural gas mains in the Rolling Greens neighborhood. During this time, parking will be restricted on both sides of the roads in this area.


In mid- or late August, another Michels Corporation crew will begin moving inside meters outside by appointment and replacing and/or reconnecting the service lines to the new main. More information about the timeline and location will be provided closer to that time.

What will CenterPoint Energy do?

For several months beginning in early August 2023, CenterPoint Energy’s authorized contractors will work along select streets in the Rolling Green neighborhood in Edina. Equix Integrity updates our records on the locations of sewer lines in relation to natural gas lines. Michels Corporation will replace natural gas mains, replace or reconnect service lines as needed, and move inside meters to the outside of homes. Q3 Contracting will restore the areas affected by Michels Corporation’s work. There will be no assessment or cost associated with our work.


For most of the project’s duration, the crews will restrict parking where they’re working. Along Interlachen Boulevard, the crew plans to close one side street at a time. Crews will coordinate access with residents. More information will be given closer to the closures’ timeframe.