​​​​​​​​​​​​​​​Edina - Normandale Road

​​​Scheduled Start Date: August 15, ​2016​​​​

​​​​Project Description ​​​​

As a system upgrade project, ​MN Limited, an authorized contractor of CenterPoint Energy, will install approximately 3,300​ feet of 24-inch steel pipe along 70th Street W. and along Normandale Road, just south of 66 Street W (see map below for detail). Construction is expected to begin August 15, 2016, and will require two months to complete the work.