​​​​​​Edina - Morningside A and White Oaks C Neighborhood 

​​​Scheduled Start Date: April 15, 2016

​​​​Project Description​​​

In preparation for a City of Edina ​roadway reconstruction project, Michels Corporation, an authorized CenterPoint Energy contractor, will be updating approximately 2,300 feet of natural gas pipelines within the Morningside A and White Oaks C Neighborhood.   

The work will also include the replacement of approximately 104 natural gas service lines. Construction is expected to begin on April 15, 2016 and will require approximately two months to complete the work. ​

Benjamin Franklin Plumbing currently has Sunnyside Road, between Curve Avenue and Townes Road, closed. 

​​​​