​​​​​Project Status - Edina - Morningside A and White Oaks C Neighborhood

Construction is finished in Edina in the Morningside A and White Oaks C Neighborhood.

7/29/2016 Update

Crews from CenterPoint Energy have finished construction in the Morningside A and White Oaks C Neighborhood in Edina. The installation of the main gas pipeline, services and restorations are completed. 

CenterPoint Energy wants to thank you for your patience.


6/6/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished street repairs in the Morningside/White Oaks neighborhood of Edina.

All the streets that are finished include Sunnyside Road, Grimes Curve Avenue, 45th Street and Townes Circle.

 

5/5/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing pipeline within the Morningside/White Oaks neighborhood of Edina.

The crew onsite is currently replacing service lines for homes located along Sunnyside Road, working from Townes Road to France Avenue S. 

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property. If the gas meter is located inside your home or building, we will move it to an outside location. 

Crews anticipate completing service line replacements in mid-May, weather permitting. Thank you.


​4/21/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will continue installing pipeline along the east side of Grimes Avenue S. and the south side of 45th street W. tomorrow, Friday, April 22.

On, Monday, April 18, crews will be installing pipeline along the south side of Townes Circle.

On Tuesday, April 26, crews will be working along Sunnyside Road, just west of France Avenue S. The alley way between Convention Grill and Hello Pizza will be closed. Access will be maintained through West 44th Street.

Please note that service line replacements will follow. An additional email will be sent once a starting date is determined.​

​4/14/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin preliminary construction and potholing in the Morningside/White Oaks neighborhood of Edina by the end of today, Thursday, April 14 or early tomorrow, Friday, April 15.

On, Monday, April 18, crews will begin installing natural gas distribution pipeline eastwards along the south side of Sunnyside Road, from Townes Road to France Avenue S. Crews anticipate working at this location through Tuesday, April 19.

Crews will then jump to Curve Avenue to install pipeline along the west side of the road for the following two days.

An additional email will be sent later next week as construction continues to progress.

Please note that the City of Edina will be moving onsite to begin total reconstruction of the road after CenterPoint Energy. Thank you.