​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Edina - Highway 62 and Tracy Avenue​​

​​​Scheduled Start Date: September 8, 2015​​​​

​​​​Project Description ​​​

As a system upgrade project, Michels Corporation, an authorized CenterPoint Energy contractor, will install approximately 2,650 feet of 24-inch steel pipe and 125 feet of 6-inch steel pipe across Highway 62, from Tracy Avenue to Holborn Avenue (see map below for detail).

Construction is expected to begin on September 8, 2015 and will require approximately six weeks to complete the work. Please anticipate traffic delays and potential lane closures as construction progresses.