4/22/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish service line replacements in the Arden Park Neighborhood by Friday, April 24th.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website for final restoration updates. Thank you.

4/13/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish installing natural gas distribution pipe in the Arden Park Neighborhood by tomorrow, Tuesday, April 14th.

Today, crews will be working at the intersections of Juanita Avenue and 52nd Street W. and along Halifax Avenue at 52nd Street W. and 54th Street W.

Service line replacements are underway along Gorgas Avenue. Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​

4/6/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe in the Arden Park Neighborhood of Edina.

Construction is underway along Halifax Avenue S., between 52nd Street W. and 54th Street W. Construction will continue for three to four days in this area.

From Tuesday to Wednesday, there will be a lane shift at 51st Street W. and Halifax Avenue S. Construction along Gorgas Avenue will begin by the end of the week.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​

3/27/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe on Monday, March 30th in the Arden Park Neighborhood of Edina.

Construction will begin along the east side of Arden Avenue, south of Bruce Place to just east of Juanita Avenue. Construction will continue for three to four days in this area.

Construction will then continue along the east side of Halifax Avenue, from 51st Street W. to  52nd Street W.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​