 10/16/2015 Update
Crews from Michels Corporation, an authorized CenterPoint Energy contractor, have finished installing natural gas distribution pipe along Flying Cloud Drive.
 
Crews from Q3, an authorized CenterPoint Energy contractor, will begin soft surface restoration next week.
 
If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042 or visit our website. Thank you.​


​10/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, installed approximately 500 feet of pipe along Flying Cloud Drive, north of Aztec Drive.

Crews are currently installing pipe southwards along the east side of Flying Cloud Drive, from just north of Collegview Drive to Sunnybrook Road.

Crews anticipate completing construction in approximately two weeks, weather permitting.

For more information, please visit our 
website. Thank you.​​


9/17/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin replacing natural gas distribution pipe along Flying Cloud Drive on Wednesday, September 23 at 7:00 a.m.

Crews will begin construction at the north end of Flying Cloud Drive, south of Anderson Lakes Parkway, and continue working southwards along the west side of the road.

Crews anticipate completing construction in approximately one month, weather permitting.

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.​​


​8/20/2015 Update

 Crews from Q3, an authorized CenterPoint Energy contractor, will finish restoration along Flying Cloud Drive, tomorrow, Friday, August 21.
 
We understand that the Flying Cloud Drive construction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we work to complete restoration as safely and quickly as possible.
 
If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042. Thank you. 


7/29/2015 Update

 Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently installing natural gas distribution pipe northwards along the southbound lanes of Flying Cloud Drive, between Singletree Lane and Leona Road.

Construction is also underway along Columbine Road, west of Prairie Drive

Please anticipate intermittent lane shifts as construction progresses for the next week along Flying Cloud Drive.

Crews anticipate completing construction by the end of the week, weather permitting. 

Restoration is underway in the completed areas of construction. For more information, please visit our website. Thank you.​
 ​​

7/21/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently installing natural gas distribution pipe northwards along the west side of Flying Cloud Drive, between Regional Center Road and Eden Road.

The current traffic control along Regional Center Road will be removed later this week.

Please anticipate intermittent lane shifts as construction progresses for the next week along Flying Cloud Drive.

For more information, please visit our website. Thank you.​


7/15/2015 Update​

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently installing natural gas distribution pipe northwards along the west side of Flying Cloud Drive at Regional Center Road.

E
astbound Regional Center Road, east of the Walgreens entrance, will be closed during construction.

Crews from Q3, an authorized CenterPoint Energy contractor, will complete restoration along Regional Center Road, west o
f the Walgreens entrance, by the weekend.

Please anticipate intermittent lane shifts as construction progresses for the next two weeks along Flying Cloud Drive.

For more information, please visit our website. Thank you. ​


7/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe along the north side of Regional Center Road, across from Commonwealth Drive, toward Flying Cloud Drive.

Please anticipate intermittent lane shifts as construction progresses.

Crews anticipate reaching Flying Cloud Drive in approximately two weeks, weather permitting.

For more information, please visit our website. Thank you. ​

6/23/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution pipe along the north side of Regional Center Road.

On Thursday, June 24th at 7:00 a.m., Regional Center Road, west of the Walmart entrance, will be closed until Thursday evening. Regional Center Road will be reopened by Friday morning. Please follow the posted detour.

Please anticipate intermittent lane shifts throughout the duration of the construction project and a future one-day full road closure of Regional Center Road in the coming weeks.

CenterPoint Energy’s construction will continue for approximately two months. Please continue to visit our website for future updates. Thank you.​​

6/17/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe west of the Columbine Road and Prairie Center Drive intersection tomorrow, Thursday, June 18th.

Crews will begin construction along the north side of Columbine Road and continue eastwards, past Prairie Center Drive, to the north side of Regional Center Road. Construction is anticipated to continue for three weeks along Regional Center Road.

The sidewalk and bike lane will be closed in this area. Please follow the posted detour.

Please anticipate intermittent lane shifts throughout the duration of the construction project and a future one-day full road closure of Regional Center Road in the coming weeks. A warning sign for the one-day closure will be posted prior to construction.

CenterPoint Energy’s construction will continue for approximately two months. Please continue to visit our website for future updates. Thank you.

12/3/2014 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will finish replacing natural gas distribution within the scope of this project by Friday, December 5th.

Temporary hard surface restoration is underway, with a full restoration occurring in the spring of 2015.

If you have questions regarding CenterPoint Energy’s restoration, please call 612-321-5042. Thank you.

11/24/2014 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, have finished replacing natural gas distribution pipe at the intersection of Columbine Road and Anderson Lakes Parkway. The bike and walking trail along Columbine Road is now restored and open to the public.

The southern lane of westbound Columbine Road at Prairie Center Drive will be shifted during the daytime as construction progresses in this area.

Construction will be closed for Thanksgiving weekend beginning Thursday, November 27th until Monday, December 1st.

Please re-visit our website to receive the final project and restoration update. Thank you.

11/13/2014 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently replacing natural gas distribution pipe at the intersection of Columbine Road and Anderson Lakes Parkway. Traffic at this intersection will continue to be reduced to one lane. Please anticipate traffic delays in this area.
Please note, construction along Flying Cloud Drive, east of Prairie Center Drive, will be postponed until next year.

Crews will continue paving the trail along Columbine Road, from Garden Lane to Anderson Lakes Parkway.

Construction is expected to be completed by the first week of December. Please re-visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

11/3/2014 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently replacing natural gas distribution pipe across the intersection of Columbine Road and Anderson Lakes Parkway.

Traffic at this intersection will be reduced to one lane for the remainder of the week. Flaggers will be directing traffic to maintain two-way traffic. Please anticipate traffic delays in this area.

On Monday, November 10th, construction at the intersection of Flying Cloud Drive and Regional Center Drive will begin.

Please re-visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

10/21/2014

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue replacing natural gas distribution pipe southwards on the west side of Columbine Road.

Construction will continue on Columbine Road, between Primrose Lane and Anderson Lakes Parkway, for the next several weeks. Southbound Columbine Road, south of Primrose Lane, will be closed as construction continues. 

Flaggers will be directing traffic to maintain two-way traffic. Please anticipate traffic delays in this area.

Beginning this week, crews will be paving Columbine Road and the trail, south of Prairie Center Drive and north of Primrose Lane.

Please re-visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

10/9/2014 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, have started replacing natural gas distribution pipe southwards on Columbine Road, west of Prairie Center Drive.

On Monday, October 20th, crews will begin construction on County Road 61. CenterPoint Energy signs will be posted today, Thursday, October 9th in the areas of construction.

Please re-visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.​​