​​​​​​​​​​​​​Crystal - 42nd Avenue N. - County Road 9

​​​Scheduled Start Date: Completed

​​​​Project Description​​​

In preparation for a July 2016 Hennepin County paving project, Michels Corporation, an authorized CenterPoint Energy contracor, upgraded 
natural gas pipelines in the spring of 2016.

Crews installed approximately 3,798 feet of 8-inch plastic pipe along 42nd Avenue N., from Louisiana Avenue N. to Adair Avenue N. The work also included the replacement of approximately 40 natural gas service lines. Construction began in early May of 2016 and was completed in July 2016.